PMI CAPM (Certified Associate in Project Management) Examination Content Outline

Practice bank
203 Qs
Real exam
150 Qs
Time limit
180 min
Passing
The passing score for the CAPM exam is not publicly disclosed by PMI. It is determined by a psychometric analysis.

Exam blueprint

Project Management Fundamentals and Core Concepts
26%
Predictive, Plan-Based Methodologies
27%
Agile Frameworks/Methodologies
17%
Business Analysis Frameworks
9%
Quality Management and Continuous Process Improvement
7%
Risk Management and Compliance
8%
Communication and Stakeholder Management
6%

Practice

Untimed · instant feedback · 4 practice tests of 90 questions

Questions per test

Custom practice

Flashcard on every question Mental map when you miss

Exam simulation

4 timed tests · 150 questions each · 180 min · pass 70% · 203 questions in the bank

+50 XP per test · +100 XP for a pass

Random simulation (weighted by domain)

Everything is open to everyone. Create a free account to save scores, XP, badges and get progress emails.

Free study resources

All resources →

Study with friends

Challenge a friend to beat your score.

PMI CAPM (Certified Associate in Project Management) Examination Content Outline practice test questions

Sample questions from the 203-question bank, with answers and explanations.

All questions
  1. 1. A project manager is overseeing a software migration project. The project is currently ahead of schedule, and the team members are highly motivated and collaborating effectively. To further enhance their capabilities and ensure continued success, the project manager decides to provide opportunities for cross-training and mentorship. Which project resource management process is the project manager primarily focused on?

    Predictive, Plan-Based Methodologies

    • A. Acquire Resources
    • B. Manage Team
    • C. Develop Team
    • D. Control Resources
    Show answer

    C. Develop Team

    The Develop Team process focuses on improving competencies, team member interaction, and the overall team environment to enhance project performance. Providing cross-training and mentorship directly aligns with improving team members' capabilities and fostering a collaborative environment, which are key objectives of this process.

  2. 2. A business analyst is facilitating a workshop with diverse stakeholders to gather requirements for a new customer relationship management (CRM) system. Several stakeholders have conflicting views on a critical feature, leading to a stalemate. Which of the following techniques should the business analyst employ to resolve this conflict and move forward?

    Business Analysis Frameworks

    • A. Exclude the conflicting stakeholders from future discussions.
    • B. Facilitate a negotiation session to find a mutually acceptable compromise.
    • C. Unilaterally decide on the feature based on their own judgment.
    • D. Escalate the decision to the project sponsor without further discussion.
    Show answer

    B. Facilitate a negotiation session to find a mutually acceptable compromise.

    When stakeholders have conflicting views, facilitating a negotiation session is the most effective way to reach a mutually acceptable compromise. This approach respects all perspectives and aims for a solution that satisfies the most critical needs while maintaining stakeholder buy-in.

  3. 3. A project manager is overseeing a construction project. The team has identified that the concrete supplier has a history of late deliveries, which could delay the project's critical path. To mitigate this, the project manager decides to order concrete from two different suppliers, even though it slightly increases the total cost. Which risk response strategy is being implemented?

    Predictive, Plan-Based Methodologies

    • A. Transfer
    • B. Exploit
    • C. Accept
    • D. Mitigate
    Show answer

    D. Mitigate

    Ordering from two suppliers to reduce the probability or impact of a late delivery from one supplier is an action taken to reduce the severity of a threat. This aligns with the 'Mitigate' risk response strategy.

  4. 4. A project manager is leading a software development project. The team has identified a high-priority risk related to a critical third-party API integration, which could cause significant delays if it fails. The project manager decides to develop a workaround plan for this specific risk, to be implemented only if the primary integration method proves unsuccessful. Which risk response strategy is being employed?

    Predictive, Plan-Based Methodologies

    • A. Accept
    • B. Contingency Planning
    • C. Mitigate
    • D. Avoid
    Show answer

    B. Contingency Planning

    Developing a workaround plan to be implemented only if a specific risk event occurs is a form of contingency planning. This strategy involves preparing predefined actions to take if a risk becomes a reality.

  5. 5. A project manager is developing the project schedule for a new software application. The team has identified various tasks, their durations, and dependencies. To accurately represent the sequence of activities and potential parallel work, which scheduling technique should the project manager primarily use?

    Predictive, Plan-Based Methodologies

    • A. Precedence Diagramming Method (PDM)
    • B. Gantt Chart
    • C. Resource Leveling
    • D. Critical Path Method (CPM)
    Show answer

    A. Precedence Diagramming Method (PDM)

    The Precedence Diagramming Method (PDM) is a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

  6. 6. A project team is developing a new mobile application. During a review session, stakeholders express concerns that a proposed feature, while technically feasible, does not align with the company's long-term strategic goal of increasing market share in a new demographic. Which requirement quality is primarily at question?

    Business Analysis Frameworks

    • A. Clarity
    • B. Testability
    • C. Completeness
    • D. Alignment
    Show answer

    D. Alignment

    Alignment refers to how well a requirement supports the overall business objectives and strategic goals. If a feature doesn't align with the company's long-term strategy, its value is questionable, even if it's otherwise well-defined.

  7. 7. A project manager is overseeing a new product development project. During the execution phase, a key stakeholder requests a significant feature addition that was not part of the approved scope. The project manager needs to evaluate this request and determine its impact on the project objectives. Which process should the project manager follow?

    Predictive, Plan-Based Methodologies

    • A. Validate Scope
    • B. Monitor and Control Project Work
    • C. Perform Integrated Change Control
    • D. Control Scope
    Show answer

    C. Perform Integrated Change Control

    Perform Integrated Change Control is the process of reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents, and the project management plan. This ensures that only approved changes are incorporated into the project.

  8. 8. A project manager is reviewing a Business Requirements Document (BRD) and notices that several requirements lack clear connections to the specific business goals they are intended to meet. The project manager emphasizes the need to establish these links to ensure that all work contributes to the project's value. Which documentation technique would best address this concern?

    Business Analysis Frameworks

    • A. Requirements traceability matrix
    • B. Data flow diagrams
    • C. Process flowcharts
    • D. Use case diagrams
    Show answer

    A. Requirements traceability matrix

    A requirements traceability matrix is specifically designed to link requirements to their sources, business objectives, design elements, and test cases, providing a clear path from need to solution.

  9. 9. A project manager is presenting the project status to key stakeholders. During the meeting, a critical stakeholder expresses confusion regarding the reporting frequency and format, stating they are not receiving the information they need in a timely or understandable manner. Which process has likely failed or needs adjustment?

    Predictive, Plan-Based Methodologies

    • A. Monitor Communications
    • B. Plan Communications Management
    • C. Manage Communications
    • D. Identify Stakeholders
    Show answer

    A. Monitor Communications

    The stakeholder's confusion about reporting frequency and format, and not receiving needed information, indicates a breakdown in ensuring that the communication needs of project stakeholders are met. This is the primary objective of the Monitor Communications process, which involves tracking and adjusting communications throughout the project.

  10. 10. A business analyst is preparing for requirements elicitation for a new internal communication platform. To ensure comprehensive coverage and minimize rework, the analyst decides to review existing company policies, current system documentation, and relevant industry standards before engaging with stakeholders. This activity is an example of which elicitation technique?

    Business Analysis Frameworks

    • A. Interviews
    • B. Workshops
    • C. Document analysis
    • D. Observation
    Show answer

    C. Document analysis

    Document analysis involves reviewing existing documentation to gather requirements and understand the current state, which aligns with reviewing company policies, system documentation, and industry standards.

  11. 11. A project manager is facilitating a meeting with key stakeholders to discuss potential project changes. During the discussion, a stakeholder expresses concerns that a proposed change might negatively impact another department not represented in the meeting. The project manager should prioritize which of the following actions immediately after this concern is raised?

    Predictive, Plan-Based Methodologies

    • A. Proceed with the discussion, noting the concern for later review.
    • B. Consult the stakeholder register to identify the impacted department's key contact.
    • C. Initiate a formal change control process immediately.
    • D. Record the change request in the change log.
    Show answer

    B. Consult the stakeholder register to identify the impacted department's key contact.

    Before recording or initiating a formal process, the project manager needs to understand the full impact of the proposed change. Consulting the stakeholder register helps identify the relevant parties whose input is crucial for a comprehensive impact analysis and proper decision-making, ensuring all affected stakeholders are considered.

  12. 12. A project manager is reviewing the project's performance. The project has a Budget at Completion (BAC) of $500,000. The Earned Value (EV) is $250,000, and the Actual Cost (AC) is $300,000. What is the Estimate at Completion (EAC) if the project manager believes that future work will be performed at the planned rate?

    Predictive, Plan-Based Methodologies

    • A. $600,000
    • B. $650,000
    • C. $700,000
    • D. $550,000
    Show answer

    D. $550,000

    If future work is performed at the planned rate, the formula for EAC is AC + (BAC - EV). Plugging in the values: $300,000 + ($500,000 - $250,000) = $300,000 + $250,000 = $550,000.

  13. 13. A project manager is initiating a large-scale construction project. A key stakeholder, the Head of Facilities, has a high level of interest in the project's outcome and significant influence over its success. However, initial interactions suggest this stakeholder is currently unsupportive due to concerns about disruption to ongoing operations. The project manager needs to determine strategies to convert this stakeholder into a supportive advocate. Which stakeholder analysis tool would be most effective for this purpose?

    Predictive, Plan-Based Methodologies

    • A. Engagement Assessment Matrix
    • B. Power/Interest Grid
    • C. Stakeholder Cube
    • D. Salience Model
    Show answer

    A. Engagement Assessment Matrix

    The Engagement Assessment Matrix (often part of the Stakeholder Engagement Plan) is used to categorize stakeholders by their current and desired levels of engagement. It helps identify gaps and determine strategies needed to move unsupportive stakeholders to a supportive stance.

  14. 14. A project manager is defining the project's scope for a new e-commerce website. The team has gathered a comprehensive list of requirements from various stakeholders. Before finalizing the scope statement, the project manager needs to ensure that all these requirements align with the project objectives and that the final product will meet the business needs. Which process group activity involves refining and elaborating these identified requirements into a detailed project scope statement?

    Predictive, Plan-Based Methodologies

    • A. Create WBS
    • B. Validate Scope
    • C. Collect Requirements
    • D. Define Scope
    Show answer

    D. Define Scope

    Define Scope is the process of developing a detailed description of the project and product. It involves taking the requirements gathered and elaborating them into a comprehensive project scope statement, including product scope description, deliverables, and acceptance criteria.

  15. 15. A business analyst is preparing for requirements elicitation for a new internal communication portal. To understand the current processes and identify pain points, the BA decides to review existing employee handbooks, company policies, and previous project documentation. What elicitation technique is the business analyst employing?

    Business Analysis Frameworks

    • A. Prototyping
    • B. Brainstorming
    • C. Interviews
    • D. Document Analysis
    Show answer

    D. Document Analysis

    Document analysis involves reviewing existing documentation to gather information about the current state, business rules, and potential requirements. This is a common and efficient way to gain initial understanding before engaging stakeholders directly.

  16. 16. A project manager is presenting the project status to key stakeholders. During the meeting, a senior executive expresses concerns about the project's communication strategy, stating that they feel uninformed about critical decisions. The project manager realizes that the current strategy is not adequately meeting the executive's needs despite following the established communication plan. Which project management process should the project manager focus on to address this issue?

    Predictive, Plan-Based Methodologies

    • A. Plan Communications Management
    • B. Manage Communications
    • C. Control Stakeholder Engagement
    • D. Monitor Communications
    Show answer

    D. Monitor Communications

    Monitor Communications is the process of ensuring the information needs of the project and its stakeholders are met. This includes evaluating the effectiveness of communication throughout the project and making adjustments as needed when stakeholders express concerns about being uninformed.

  17. 17. A project manager is managing a complex IT infrastructure upgrade. The project team has identified several risks, including a potential failure of a critical server component. To address this, they decide to procure a backup server and have it ready for immediate deployment if the primary server fails. Which risk response strategy is being employed?

    Predictive, Plan-Based Methodologies

    • A. Transfer
    • B. Avoid
    • C. Mitigate
    • D. Accept
    Show answer

    C. Mitigate

    Mitigation is a risk response strategy where actions are taken to reduce the probability or impact of a risk event. Procuring a backup server reduces the impact of a primary server failure, thus it is a mitigation strategy.

  18. 18. A business analyst is reviewing a set of functional requirements for a new inventory management system. One requirement states: 'The system should be user-friendly.' Which characteristic of a SMART requirement is MOST notably missing or poorly defined in this statement?

    Business Analysis Frameworks

    • A. Measurable
    • B. Specific
    • C. Relevant
    • D. Achievable
    Show answer

    A. Measurable

    The term 'user-friendly' is subjective and not measurable. To make this a SMART requirement, it would need quantitative criteria, such as 'The system should allow a new user to complete an inventory search within 30 seconds with no more than 2 errors.' This makes it measurable.

  19. 19. A project manager is developing the project management plan for a new product development project. The team has identified several high-priority risks that could significantly impact the project objectives. To address the uncertainty associated with these identified risks, the project manager should include a specific amount of budget and schedule in the cost and schedule baselines. What is this amount called?

    Predictive, Plan-Based Methodologies

    • A. Contingency Reserve
    • B. Cost Baseline
    • C. Budget at Completion (BAC)
    • D. Management Reserve
    Show answer

    A. Contingency Reserve

    Contingency reserves are budget and schedule amounts held to address identified risks (known-unknowns). They are part of the cost and schedule baselines. Management reserves, on the other hand, are for unknown-unknowns and are not part of the project's cost baseline.

  20. 20. A project manager is developing a new, complex IT system. The project involves multiple teams, external vendors, and highly specialized technical work. To ensure that all project tasks are completed by the appropriate resources and that the team understands their roles and responsibilities, the project manager creates a chart that visually displays the assigned roles, responsibilities, and authority for each work package. Which tool or technique is the project manager using?

    Predictive, Plan-Based Methodologies

    • A. Hierarchical Type Organizational Chart
    • B. Responsibility Assignment Matrix (RAM)
    • C. Resource Breakdown Structure (RBS)
    • D. Organizational Breakdown Structure (OBS)
    Show answer

    B. Responsibility Assignment Matrix (RAM)

    A Responsibility Assignment Matrix (RAM) is a grid that shows the project resources assigned to each work package. It clearly defines roles, responsibilities, and authority, often using a RACI (Responsible, Accountable, Consulted, Informed) chart.

  21. 21. A project manager is overseeing a software migration project. The project is currently ahead of schedule and under budget. The team's morale is high, and they are performing exceptionally well. The project manager wants to acknowledge this outstanding performance and ensure it continues. Which of the following actions would be most appropriate for the project manager to take to reward and recognize the team?

    Predictive, Plan-Based Methodologies

    • A. Reassign high-performing team members to more challenging, individual tasks.
    • B. Implement stricter performance metrics to maintain the current pace.
    • C. Update the project management plan to reduce future budget allocations.
    • D. Document the team's achievements and provide public recognition.
    Show answer

    D. Document the team's achievements and provide public recognition.

    Public recognition and documentation of achievements are key motivators and part of effective team management. This reinforces positive behavior and encourages continued high performance, aligning with the Develop Team process.

  22. 22. A business analyst is reviewing a set of functional requirements for a new inventory management system. One requirement states, 'The system shall allow users to search for products.' This requirement is considered incomplete and ambiguous. To improve its quality, the analyst should ensure it meets which characteristic of a good requirement?

    Business Analysis Frameworks

    • A. Relevant
    • B. Attainable
    • C. Measurable
    • D. Time-bound
    Show answer

    C. Measurable

    To make the requirement 'The system shall allow users to search for products' less ambiguous and more complete, it needs to be measurable. This means specifying criteria such as search speed, search fields, and result display, which can be verified.

  23. 23. A project manager is developing the project schedule for a complex engineering project. The team has identified various activities and their dependencies. To represent these activities and their logical relationships in a graphical format, which tool or technique should be used?

    Predictive, Plan-Based Methodologies

    • A. Precedence Diagramming Method (PDM)
    • B. Critical Path Method (CPM)
    • C. Resource Leveling
    • D. Gantt Chart
    Show answer

    A. Precedence Diagramming Method (PDM)

    The Precedence Diagramming Method (PDM) is a technique used for constructing a project schedule network diagram that uses nodes to represent activities and arrows to represent logical relationships between them. This directly addresses the need to represent activities and their relationships graphically.

  24. 24. A project manager is developing the project management plan for a new product launch. The project involves multiple external vendors for specialized components and services. To ensure that all necessary external resources are acquired effectively and legally, which subsidiary plan should the project manager develop?

    Predictive, Plan-Based Methodologies

    • A. Stakeholder Engagement Plan
    • B. Communications Management Plan
    • C. Procurement Management Plan
    • D. Resource Management Plan
    Show answer

    C. Procurement Management Plan

    The Procurement Management Plan describes how a project team will acquire goods and services from outside the performing organization. Since the project involves multiple external vendors, developing this plan is crucial for managing these external acquisitions effectively and legally.

  25. 25. A business analyst is defining the approach for how requirements will be gathered, analyzed, and managed throughout a project. Which of the following activities is MOST critical to perform during the business analysis planning phase?

    Business Analysis Frameworks

    • A. Identifying and categorizing all project stakeholders.
    • B. Developing the detailed solution design.
    • C. Conducting user acceptance testing (UAT).
    • D. Writing the final project status report.
    Show answer

    A. Identifying and categorizing all project stakeholders.

    During the business analysis planning phase, identifying and categorizing stakeholders is crucial because it determines who needs to be involved in requirements activities and how they will be engaged. This foundational step ensures all relevant perspectives are considered.

PMI CAPM (Certified Associate in Project Management) Examination Content Outline flashcards

Tap a card to flip it. 161 flashcards in the full deck.

  • Develop Team

    Flip card

    The process of improving competencies, team member interaction, and the overall team environment to enhance project performance.

    • Focuses on individual and team growth.
    • Includes training, coaching, recognition, and team-building activities.
    • Aims to enhance skills, improve relationships, and foster trust.
    Study this card →
  • Conflict Resolution (BA)

    Flip card

    Conflict resolution in business analysis involves techniques used to address disagreements among stakeholders regarding requirements or proposed solutions to reach a consensus or acceptable compromise.

    • Essential for managing diverse stakeholder needs.
    • Aims for mutually acceptable solutions.
    • Often involves negotiation and mediation techniques.
    Study this card →
  • Mitigate Risk

    Flip card

    A risk response strategy where actions are taken to reduce the probability of a threat occurring or to reduce its impact if it does occur.

    • Involves proactive steps to lessen risk exposure.
    • Does not eliminate the risk entirely, but reduces its severity.
    • Examples include redundant systems, additional testing, or choosing more reliable suppliers.
    Study this card →
  • Contingency Planning

    Flip card

    A risk response strategy that involves developing a plan for what to do if a specific risk event occurs. It's a proactive approach to address risks that are not avoided or fully mitigated.

    • Prepares for potential risk realization.
    • Often includes fallback plans or workarounds.
    • Distinct from general mitigation, as it's a 'what if' scenario plan.
    Study this card →
  • Precedence Diagramming Method (PDM)

    Flip card

    A technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.

    • Activities are represented as nodes.
    • Links show dependencies (finish-to-start, start-to-start, etc.).
    • Foundation for critical path analysis.
    Study this card →
  • Requirement Quality: Alignment

    Flip card

    Alignment ensures that a requirement directly supports and contributes to the project's objectives and the organization's strategic goals. Misaligned requirements can lead to wasted effort.

    • Links requirements to business objectives.
    • Prevents scope creep from irrelevant features.
    • Ensures value delivery.
    Study this card →
  • Integrated Change Control

    Flip card

    The process of reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents, and the project management plan.

    • Ensures only approved changes are incorporated.
    • Involves reviewing, approving, and managing changes.
    • Aims to maintain project integrity and alignment with objectives.
    Study this card →
  • Requirements Traceability Matrix (RTM)

    Flip card

    A document that links requirements to other requirements, design elements, test cases, and business objectives, ensuring all requirements are accounted for and aligned.

    • Provides a clear audit trail for requirements.
    • Helps manage scope, risk, and change.
    • Ensures business value is delivered by connecting requirements to goals.
    Study this card →
  • Monitor Communications

    Flip card

    The process of ensuring the information needs of the project and its stakeholders are met.

    • Evaluates the effectiveness of communication activities.
    • Identifies gaps or inefficiencies in the communication flow.
    • May lead to updates in the communications management plan.
    Study this card →
  • Document Analysis (Elicitation)

    Flip card

    A requirements elicitation technique that involves reviewing existing documentation to understand the current state, identify business rules, and uncover potential requirements.

    • Cost-effective and can be done before stakeholder engagement.
    • Helps identify 'as-is' processes and existing constraints.
    • Can provide a baseline for discussions with stakeholders.
    Study this card →
  • Manage Stakeholder Engagement

    Flip card

    The process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.

    • Aims to increase support and minimize resistance.
    • Requires continuous communication and conflict resolution.
    • Relies on regular review of the stakeholder register.
    Study this card →
  • Estimate at Completion (EAC)

    Flip card

    The expected total cost of completing all work on a project or work package.

    • Calculated based on project performance to date and assumptions about future performance.
    • Different formulas exist depending on assumptions about future performance.
    • Provides a forecast for the total project cost.
    Study this card →
  • Engagement Assessment Matrix

    Flip card

    A tool used in stakeholder analysis to compare the current engagement level of stakeholders with their desired engagement level. It helps in identifying gaps and developing strategies to move stakeholders to the desired level of support.

    • Compares current vs. desired engagement.
    • Helps identify engagement gaps.
    • A key input for developing engagement strategies.
    Study this card →
  • Define Scope

    Flip card

    The process of developing a detailed description of the project and product. It involves elaborating on the requirements gathered to create a comprehensive project scope statement.

    • Creates the project scope statement.
    • Refines and elaborates collected requirements.
    • Forms the basis for future project work.
    Study this card →
  • Risk Mitigation

    Flip card

    A risk response strategy where actions are taken to reduce the probability or impact of a threat, or to increase the probability or impact of an opportunity.

    • Aims to lessen severity or likelihood of risk.
    • Does not eliminate the risk, but reduces its effect.
    • Examples include backup plans, enhanced testing, training.
    Study this card →
  • SMART Requirements: Measurable

    Flip card

    A measurable requirement includes criteria that can be used to determine if the requirement has been successfully met. It answers 'how much, how many, or how often?'

    • Quantifiable success criteria.
    • Allows for objective verification.
    • Avoids subjective interpretations.
    Study this card →
  • Contingency Reserve

    Flip card

    Budget or schedule amounts added to the cost or schedule baseline to account for identified risks (known-unknowns).

    • Part of the project's cost and schedule baselines.
    • Used to mitigate the impact of specific, identified risks.
    • Estimated using quantitative risk analysis methods.
    Study this card →
  • Responsibility Assignment Matrix (RAM)

    Flip card

    A grid that shows the project resources assigned to each work package, identifying who is responsible, accountable, consulted, and informed (RACI) for specific tasks or deliverables.

    • Maps roles and responsibilities to work packages.
    • Commonly uses the RACI model.
    • Ensures clear understanding of task ownership and involvement.
    Study this card →
  • Procurement Management Plan

    Flip card

    A subsidiary plan of the project management plan that describes how a project team will acquire goods and services from outside the performing organization.

    • Defines the procurement process from planning to contract closure.
    • Covers types of contracts, metrics, and roles.
    • Essential when external vendors or suppliers are involved.
    Study this card →
  • Business Analysis Planning

    Flip card

    Business analysis planning involves determining the approach for performing business analysis activities on a given project. It sets the foundation for how requirements will be managed.

    • Defines the 'how' of business analysis.
    • Occurs early in the project lifecycle.
    • Ensures a structured approach to requirements.
    Study this card →
  • Requirements Management Plan

    Flip card

    A component of the project or program management plan that describes how requirements will be analyzed, documented, and managed.

    • Defines the process for requirements activities.
    • Covers prioritization, verification, and validation.
    • Outlines how changes to requirements will be managed.
    Study this card →
  • Plan Risk Management

    Flip card

    The process of defining how to conduct risk management activities for a project.

    • Establishes the approach for risk management.
    • Determines risk tolerances and thresholds.
    • Defines roles and responsibilities for risk activities.
    Study this card →
  • Stakeholder Engagement Plan

    Flip card

    A component of the project management plan that describes how stakeholders will be effectively involved in the project.

    • Identifies strategies and actions for productive stakeholder involvement.
    • Aims to manage expectations and foster support.
    • Output of the Plan Stakeholder Engagement process.
    Study this card →
  • Create WBS

    Flip card

    The process of subdividing project deliverables and project work into smaller, more manageable components.

    • Hierarchical decomposition of total scope.
    • Breaks down work into work packages.
    • Foundation for planning cost, schedule, and resources.
    Study this card →

Questions are original practice items written to match the published exam objectives. Step2Study is not affiliated with or endorsed by any certification body.