A project manager is reviewing the project's performance. The project has a Budget at Completion (BAC) of $500,000. The Earned Value (EV) is $250,000, and the Actual Cost (AC) is $300,000. What is the Estimate at Completion (EAC) if the project manager believes that future work will be performed at the planned rate?

  1. A$600,000
  2. B$650,000
  3. C$700,000
  4. D$550,000
Show answer & explanation

Correct answer: D. $550,000

If future work is performed at the planned rate, the formula for EAC is AC + (BAC - EV). Plugging in the values: $300,000 + ($500,000 - $250,000) = $300,000 + $250,000 = $550,000.

Why the other options are wrong

  • A. Incorrect calculation, possibly using a different EAC formula or miscalculation.
  • B. Incorrect calculation, possibly using a different EAC formula or miscalculation.
  • C. Incorrect calculation, possibly using a different EAC formula or miscalculation.

Estimate at Completion (EAC)

The expected total cost of completing all work on a project or work package.

  • Calculated based on project performance to date and assumptions about future performance.
  • Different formulas exist depending on assumptions about future performance.
  • Provides a forecast for the total project cost.

Memory trick: EAC: Estimate how much money you'll need to Finish (BAC) based on how you're doing (EV, AC).