PMI CAPM (Certified Associate in Project Management) Examination Content OutlinePredictive, Plan-Based MethodologiesMedium

A project manager is developing the project management plan for a new product development project. The team has identified several high-priority risks that could significantly impact the project objectives. To address the uncertainty associated with these identified risks, the project manager should include a specific amount of budget and schedule in the cost and schedule baselines. What is this amount called?

  1. AContingency Reserve
  2. BCost Baseline
  3. CBudget at Completion (BAC)
  4. DManagement Reserve
Show answer & explanation

Correct answer: A. Contingency Reserve

Contingency reserves are budget and schedule amounts held to address identified risks (known-unknowns). They are part of the cost and schedule baselines. Management reserves, on the other hand, are for unknown-unknowns and are not part of the project's cost baseline.

Why the other options are wrong

  • B. Cost Baseline is the approved budget for the project, which includes contingency reserves, but it's not the reserve itself.
  • C. Budget at Completion (BAC) is the total planned budget for the project, not a specific reserve for risks.
  • D. Management Reserve is for unknown-unknown risks and is not part of the project's cost baseline.

Contingency Reserve

Budget or schedule amounts added to the cost or schedule baseline to account for identified risks (known-unknowns).

  • Part of the project's cost and schedule baselines.
  • Used to mitigate the impact of specific, identified risks.
  • Estimated using quantitative risk analysis methods.

Memory trick: Reserves: Contingency for Knowns, Management for Unknowns.

More Predictive, Plan-Based Methodologies questions