PMI CAPM (Certified Associate in Project Management) Examination Content OutlinePredictive, Plan-Based MethodologiesMedium

A project manager is leading a software development project. The team has identified a high-priority risk related to a critical third-party API integration, which could cause significant delays if it fails. The project manager decides to develop a workaround plan for this specific risk, to be implemented only if the primary integration method proves unsuccessful. Which risk response strategy is being employed?

  1. AAccept
  2. BContingency Planning
  3. CMitigate
  4. DAvoid
Show answer & explanation

Correct answer: B. Contingency Planning

Developing a workaround plan to be implemented only if a specific risk event occurs is a form of contingency planning. This strategy involves preparing predefined actions to take if a risk becomes a reality.

Why the other options are wrong

  • A. Acceptance involves no proactive action, whereas a workaround plan is a proactive preparation.
  • C. Mitigation reduces the probability or impact of a risk, but a workaround for a failed primary approach is a specific response, not a general reduction.
  • D. Avoidance eliminates the risk entirely, which is not the case here as the primary integration is still planned.

Contingency Planning

A risk response strategy that involves developing a plan for what to do if a specific risk event occurs. It's a proactive approach to address risks that are not avoided or fully mitigated.

  • Prepares for potential risk realization.
  • Often includes fallback plans or workarounds.
  • Distinct from general mitigation, as it's a 'what if' scenario plan.

Memory trick: Avoid, Transfer, Mitigate, Accept, and Plan for Contingencies.