PMI CAPM (Certified Associate in Project Management) Examination Content OutlineProject Management Fundamentals and Core ConceptsEasy

A project manager is leading a software development project for a client who has provided detailed requirements and expects a fixed scope and budget. The project environment is stable with minimal anticipated changes. Which project life cycle approach is most suitable for this project?

  1. AHybrid
  2. BIterative
  3. CAdaptive
  4. DPredictive
Show answer & explanation

Correct answer: D. Predictive

A predictive life cycle is best suited when requirements are well-defined, the scope is stable, and there is a low degree of uncertainty. This allows for detailed planning upfront.

Why the other options are wrong

  • A. Hybrid life cycles combine elements, but predictive is best when requirements are fully known.
  • B. Iterative life cycles are for evolving requirements with repeated cycles, not fixed scope.
  • C. Adaptive life cycles are for high uncertainty and evolving requirements.

Predictive Life Cycle

A project life cycle in which the project scope, time, and cost are determined in the early phases of the life cycle.

  • Also known as waterfall or plan-driven.
  • Requirements are stable and well-defined upfront.
  • Changes are carefully managed and often costly.

Memory trick: Predictive's plan-driven path is clear.