PMI CAPM (Certified Associate in Project Management) Examination Content OutlineProject Management Fundamentals and Core ConceptsMedium

A project manager is leading a project where the overall approach is to define detailed requirements upfront, create a comprehensive plan, and then execute the project in sequential phases with minimal changes expected. Which project life cycle is being utilized?

  1. AAdaptive
  2. BIterative
  3. CPredictive
  4. DHybrid
Show answer & explanation

Correct answer: C. Predictive

A predictive life cycle (also known as a waterfall or plan-driven approach) is characterized by defining detailed requirements upfront, creating a comprehensive plan, and then executing the project in sequential phases. It assumes that the project environment is stable and that changes will be minimal.

Why the other options are wrong

  • A. Adaptive life cycles are for projects with high uncertainty and evolving requirements.
  • B. Iterative life cycles involve repeating cycles of planning and execution, suitable for projects where requirements are refined over time.
  • D. Hybrid life cycles combine elements of both predictive and adaptive approaches.

Predictive Life Cycle

A project life cycle approach where the project scope, time, and cost are determined early in the project life cycle, with detailed planning and sequential execution phases.

  • Detailed requirements defined upfront.
  • Comprehensive plan developed early.
  • Sequential phases (e.g., Waterfall).
  • Assumes stable environment and minimal changes.

Memory trick: Predictive projects are like building a bridge: plan every detail before you start.