On a CPM schedule, the critical path through the project totals 20 days. A parallel sequence of activities (Path B) that must also be completed totals 15 days. What is the total float available for Path B?

  1. A15 days
  2. B20 days
  3. C0 days
  4. D5 days
Show answer & explanation

Correct answer: D. 5 days

Float is the amount of time an activity or path can be delayed without affecting the project's overall completion date. Since the critical path is 20 days and Path B only requires 15 days, Path B has 20 - 15 = 5 days of float before it becomes critical.

Why the other options are wrong

  • A. This is Path B's duration, not its float.
  • B. This is the critical path duration, not the float value.
  • C. Zero float describes the critical path itself, not Path B.

CPM Float Calculation

Float is the scheduling slack for a non-critical path, calculated as the difference between the critical path duration and that path's own duration.

  • Critical path activities have zero float
  • Float = critical path duration minus path duration
  • Using up float on a path can make it become critical

Memory trick: The critical path has no slack; everything else has some.