CSLB General Building (B)Planning and EstimatingEasy

A homeowner hires a licensed contractor to build a new detached garage. Before any construction begins, who is responsible for obtaining the building permit from the local building department?

  1. AThe homeowner, since it is their property
  2. BThe contractor performing the work
  3. CThe building inspector assigned to the project
  4. DThe architect who prepared the plans
Show answer & explanation

Correct answer: B. The contractor performing the work

Under standard practice and CSLB expectations, the licensed contractor performing the work is responsible for obtaining permits unless a specific owner-builder exemption applies. The contractor ensures the work is authorized and inspected properly.

Why the other options are wrong

  • A. Homeowners only pull permits themselves under an owner-builder exemption, not when hiring a licensed contractor.
  • C. Inspectors review and approve work; they do not obtain permits.
  • D. Architects prepare plans but are not responsible for permit acquisition.

Permit Responsibility

The party legally obligated to secure building permits before construction begins, typically the contractor performing the licensed work.

  • Contractors normally pull permits for work under their license
  • Owner-builder exemptions allow homeowners to pull permits themselves
  • Unpermitted work can result in fines and stop-work orders

Memory trick: The one swinging the hammer gets the paper first.