CSLB General Building (B)Planning and EstimatingMedium

A project scheduler wants a visual tool that displays each construction task as a horizontal bar along a timeline, showing start and finish dates for framing, roofing, and drywall. Which scheduling tool best serves this purpose?

  1. ABar coding manifest
  2. BGantt chart
  3. CCritical path method diagram
  4. DPull plan schedule
Show answer & explanation

Correct answer: B. Gantt chart

A Gantt chart displays tasks as horizontal bars plotted against a timeline, clearly showing the start and finish dates and duration of each activity. This makes it ideal for tracking overall project progress at a glance.

Why the other options are wrong

  • A. This is not a recognized construction scheduling term.
  • C. CPM diagrams show task dependencies and float, not simple timeline bars.
  • D. Pull planning is a collaborative lean scheduling technique, not a bar chart.

Gantt Chart

A scheduling tool that represents project tasks as horizontal bars along a calendar timeline, showing duration, start, and finish dates.

  • Bars represent task duration visually
  • Easy to read overall project timeline at a glance
  • Does not always show task dependencies like CPM does

Memory trick: Bars on a calendar mean Gantt, not chance.