CSLB General Building (B)Site Work, Foundations and ConcreteHard

A contractor needs to order ready-mix concrete for a rectangular footing measuring 30 feet long, 2 feet wide, and 1 foot deep. How many cubic yards of concrete should be ordered (rounded up to the nearest quarter yard)?

  1. A3.0 cubic yards
  2. B2.0 cubic yards
  3. C1.5 cubic yards
  4. D2.25 cubic yards
Show answer & explanation

Correct answer: D. 2.25 cubic yards

Volume = 30 ft x 2 ft x 1 ft = 60 cubic feet. Converting to cubic yards: 60 ÷ 27 = 2.22 cubic yards, which rounds up to 2.25 cubic yards to ensure enough material for the pour.

Why the other options are wrong

  • A. 3.0 cubic yards significantly overestimates the needed volume, wasting material and cost.
  • B. 2.0 cubic yards (54 cubic feet) is still short of the required 60 cubic feet.
  • C. 1.5 cubic yards would be insufficient, covering only about 40.5 cubic feet.

Concrete Volume Calculation

Concrete quantity is calculated by finding volume in cubic feet (L x W x H) and converting to cubic yards by dividing by 27.

  • 1 cubic yard = 27 cubic feet
  • Formula: Volume (cf) = Length x Width x Depth
  • Always round up when ordering to avoid running short during a pour

Memory trick: 27 cubic feet make a yard — divide and round to avoid falling hard.