Master Electrician Exam (NEC)Load CalculationsMedium

A commercial building has a total connected general lighting load of 45,000 VA. This load is considered continuous. What is the minimum feeder capacity required for this lighting load?

  1. A33,750 VA
  2. B67,500 VA
  3. C45,000 VA
  4. D56,250 VA
Show answer & explanation

Correct answer: D. 56,250 VA

According to NEC 210.20(A) and 215.2(A)(1), continuous loads must be multiplied by a factor of 125% (or 1.25) when sizing branch circuits and feeders. Therefore, the minimum feeder capacity required for a continuous lighting load of 45,000 VA is 45,000 VA * 1.25 = 56,250 VA.

Why the other options are wrong

  • A. This would be 75% of the connected load, which is incorrect for continuous loads.
  • B. This value is incorrect and results from an incorrect multiplier.
  • C. This is the connected load, but it does not account for the continuous nature of the load.

Continuous Load Factor

A continuous load is a load where the maximum current is expected to continue for 3 hours or more. For such loads, the branch-circuit or feeder overcurrent device rating must not be less than 125% of the continuous load current.

  • Continuous loads operate for 3 hours or more.
  • NEC requires sizing at 125% of the continuous load.
  • This factor applies to overcurrent devices and conductor ampacity.

Memory trick: Long run, extra strength. Always 125 percent.