PMI CAPM (Certified Associate in Project Management) Examination Content OutlineProject Management Fundamentals and Core ConceptsEasy

A project manager is developing a project document that outlines the business need, high-level project description, and the project manager's assigned authority. Which document is the project manager creating?

  1. AStakeholder Register
  2. BProject Management Plan
  3. CScope Statement
  4. DProject Charter
Show answer & explanation

Correct answer: D. Project Charter

The Project Charter is the document that formally authorizes the existence of a project, provides the project manager with the authority to apply organizational resources, and outlines high-level project information including the business need and project description.

Why the other options are wrong

  • A. The Stakeholder Register is a list of project stakeholders and their relevant information, not the document authorizing the project.
  • B. The Project Management Plan details how the project will be executed, monitored, controlled, and closed, not its initial authorization.
  • C. The Scope Statement describes the project deliverables, exclusions, and acceptance criteria in detail, which comes after the charter.

Project Charter

A document issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

  • Formalizes project existence.
  • Grants PM authority.
  • Contains high-level project information.

Memory trick: Charter is the 'key' to starting a project.