PMI CAPM (Certified Associate in Project Management) Examination Content OutlinePredictive, Plan-Based MethodologiesEasy

A project manager is overseeing a large-scale construction project. The team has just completed the concrete pouring for the foundation and is now preparing to erect the structural steel. Which project management process group is the project manager primarily working within?

  1. APlanning
  2. BMonitoring and Controlling
  3. CInitiating
  4. DExecuting
Show answer & explanation

Correct answer: D. Executing

The scenario describes activities related to carrying out the project work as defined in the project management plan, which falls under the Executing Process Group. Initiating, Planning, and Monitoring and Controlling occur at different stages or involve different types of activities.

Why the other options are wrong

  • A. Planning involves defining and refining objectives, and planning the course of action required to attain project objectives.
  • B. Monitoring and Controlling involves tracking, reviewing, and regulating the progress and performance of the project.
  • C. Initiating involves defining a new project or a new phase by obtaining authorization.

Executing Process Group

The Executing Process Group consists of the processes performed to complete the work defined in the project management plan to satisfy the project requirements.

  • Focuses on carrying out the work as planned.
  • Involves managing resources, implementing activities, and producing deliverables.
  • Generates work performance data.

Memory trick: I Plan Every Move Carefully, Closing projects with ease.

More Predictive, Plan-Based Methodologies questions