PMI CAPM (Certified Associate in Project Management) Examination Content OutlinePredictive, Plan-Based MethodologiesEasy
A project manager is developing the project charter. Which of the following is a primary input required for this process?
- ARisk Register
- BBusiness Documents
- CWork Performance Data
- DChange Log
Show answer & explanationAnswer & explanation
Correct answer: B. Business Documents
The Business Documents, specifically the Business Case and Benefits Management Plan, are crucial inputs for developing the project charter, as they justify the project and its expected outcomes.
Why the other options are wrong
- A. The Risk Register is an output of risk management processes, not an input to the project charter.
- C. Work Performance Data is generated during project execution and monitoring, not during the initiation phase when the charter is developed.
- D. The Change Log is a document used to record change requests, which occurs later in the project lifecycle.
Develop Project Charter Inputs
The essential information and documents required to formally authorize a project and appoint a project manager.
- Business Documents (Business Case, Benefits Management Plan)
- Agreements
- Enterprise Environmental Factors (EEFs)
- Organizational Process Assets (OPAs)
Memory trick: Business Agreements and Org Factors are the Charter's core.