PMI CAPM (Certified Associate in Project Management) Examination Content OutlineProject Management Fundamentals and Core ConceptsEasy

A project manager is working on a project to develop a new accounting software. The project's requirements are well-defined, and the client has a clear vision of the final product. Which project life cycle approach would be most suitable for this project?

  1. APredictive Life Cycle
  2. BIterative Life Cycle
  3. CHybrid Life Cycle
  4. DAdaptive Life Cycle
Show answer & explanation

Correct answer: A. Predictive Life Cycle

A Predictive Life Cycle is best suited for projects with well-defined requirements and a clear scope from the outset, as described in the scenario. This approach allows for detailed planning upfront.

Why the other options are wrong

  • B. Iterative life cycles involve repeated cycles of planning and execution, suitable when requirements are understood but evolve over time, offering more flexibility than predictive but less than adaptive.
  • C. Hybrid life cycles combine elements of both predictive and adaptive approaches, typically for projects with some stable and some evolving components.
  • D. Adaptive life cycles are used when requirements are uncertain or evolve rapidly, which is not the case here.

Predictive Life Cycle

A project life cycle approach where the project scope, time, and cost are determined early in the project life cycle.

  • Requirements are well-understood and stable.
  • Detailed planning occurs upfront.
  • Often called 'waterfall' approach.

Memory trick: Clear roadmap means predictive path.