CSLB General Building (B)Planning and EstimatingMedium

A contractor is planning to pour a concrete driveway that is 60 feet long, 10 feet wide, and 4 inches thick. If concrete is ordered in full cubic yard increments, how many cubic yards of concrete should be ordered to account for standard waste?

  1. A6 cubic yards
  2. B8 cubic yards
  3. C10 cubic yards
  4. D12 cubic yards
Show answer & explanation

Correct answer: B. 8 cubic yards

First, calculate the volume in cubic feet (60 ft * 10 ft * 0.333 ft = 199.8 cubic feet). Convert to cubic yards by dividing by 27 (199.8 / 27 = 7.4 cubic yards). With a standard 10% waste factor, this becomes 7.4 * 1.10 = 8.14 cubic yards. Since concrete is ordered in full cubic yard increments, 8 cubic yards is the closest full yard without going under the required amount, considering the waste factor.

Why the other options are wrong

  • A. Incorrect; this does not account for the correct volume or waste factor.
  • C. Incorrect; this overestimates the required concrete significantly.
  • D. Incorrect; this significantly overestimates the required concrete.

Concrete Volume & Waste

Estimating concrete volume involves calculating cubic feet, converting to cubic yards, and adding a waste factor (typically 5-10%) before rounding up to the nearest full yard for ordering.

  • 1 cubic yard = 27 cubic feet
  • Common waste factor: 5-10%
  • Always round up to the nearest full cubic yard for ordering

Memory trick: Calculate, Convert, Cushion, Confirm!