PMI CAPM (Certified Associate in Project Management) Examination Content OutlineProject Management Fundamentals and Core ConceptsMedium

A project manager is reviewing a document that outlines the business need, high-level project description, and assigns the project manager with the authority to apply organizational resources. Which project document is being reviewed?

  1. AProject Charter
  2. BRequirements Documentation
  3. CProject Management Plan
  4. DScope Statement
Show answer & explanation

Correct answer: A. Project Charter

The Project Charter is the document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. It typically includes the business need and a high-level description.

Why the other options are wrong

  • B. Requirements Documentation describes how individual requirements meet the business need, not the project's formal authorization.
  • C. The Project Management Plan is a comprehensive document detailing how the project will be executed, monitored, and controlled, not initial authorization.
  • D. The Scope Statement provides a detailed description of the project and product scope, but doesn't formally authorize the project or PM's authority.

Project Charter Purpose

The Project Charter formally authorizes a project and grants the project manager the authority to apply organizational resources.

  • Created in the Initiating Process Group.
  • Provides a high-level overview of the project.
  • Signed by the project sponsor or initiator.

Memory trick: The Charter is the 'key' to unlock resources and start the project journey.