PMI CAPM (Certified Associate in Project Management) Examination Content OutlineProject Management Fundamentals and Core ConceptsMedium

A project manager is leading a team developing a new medical device. Due to stringent regulatory requirements and the need for precision, the team adheres strictly to a detailed plan created upfront. Changes are carefully controlled through a formal process. Which project life cycle approach is being utilized?

  1. AHybrid
  2. BAdaptive
  3. CPredictive
  4. DIterative
Show answer & explanation

Correct answer: C. Predictive

A predictive life cycle (often called waterfall) is characterized by defining the scope, schedule, and cost early in the project. It emphasizes detailed upfront planning and a formal change control process, which is ideal for projects with stable requirements and high regulatory compliance, like medical devices.

Why the other options are wrong

  • A. A hybrid approach combines elements, but the scenario strongly emphasizes the 'predictive' aspects without mentioning adaptive components.
  • B. Adaptive life cycles embrace change and are iterative, not characterized by strict upfront planning and formal change control.
  • D. Iterative life cycles involve repeating phases to refine the product, but not necessarily with the strict upfront planning and change control described.

Predictive Life Cycle

A project life cycle approach where the scope, time, and cost are determined early in the project life cycle, and changes are tightly controlled.

  • Detailed upfront planning.
  • Sequential phases (e.g., waterfall).
  • Low tolerance for change.
  • Suitable for stable requirements.

Memory trick: Predictive plans everything, Adaptive adapts to anything.