PMI CAPM (Certified Associate in Project Management) Examination Content OutlineProject Management Fundamentals and Core ConceptsHard

A project manager is working in a functional organization where resources are highly specialized and report directly to their functional managers. The project manager needs a specific developer for a critical task, but the developer's functional manager is prioritizing another operational task. Which of the following is the MOST appropriate initial action for the project manager to take?

  1. AFormally request the resource through the functional manager, highlighting the project's priority and impact.
  2. BEscalate the issue directly to the project sponsor.
  3. CWait until the developer's operational task is completed.
  4. DAssign the task to another available team member, even if they lack the specialized skill.
Show answer & explanation

Correct answer: A. Formally request the resource through the functional manager, highlighting the project's priority and impact.

In a functional organization, the project manager has limited authority. The most appropriate initial action is to work through the formal channels by making a strong case to the functional manager, emphasizing the project's priority and potential impact of delay. Escalation is a later step if this fails.

Why the other options are wrong

  • B. Escalation is generally a secondary step if direct negotiation fails, as it can strain relationships.
  • C. Waiting passively is not proactive project management and can lead to project delays.
  • D. Assigning to an unqualified team member risks quality and project failure.

Project Manager Role in Functional Organization

In a functional organization, the project manager typically has a limited role, often acting as a project coordinator or expediter, with little formal authority over resources.

  • Relies heavily on negotiation and influence.
  • Formal communication channels are crucial.
  • Functional managers retain ultimate control over resources.

Memory trick: Functional PM Persuades, Prioritizes, and Plans.

More Project Management Fundamentals and Core Concepts questions