PMI CAPM (Certified Associate in Project Management) Examination Content OutlinePredictive, Plan-Based MethodologiesMedium

A project manager is defining the project's scope for a new e-commerce website. The team has gathered all requirements and is now in the process of developing a detailed description of the project and product. Which project scope management process is the project manager currently performing?

  1. APlan Scope Management
  2. BCollect Requirements
  3. CCreate WBS
  4. DDefine Scope
Show answer & explanation

Correct answer: D. Define Scope

The Define Scope process involves developing a detailed description of the project and product. This process takes the requirements collected and elaborates them into a clear, comprehensive scope statement, which is precisely what the project manager is doing after gathering requirements.

Why the other options are wrong

  • A. Plan Scope Management is about how scope will be managed, not defining the scope itself.
  • B. Collect Requirements is about gathering and documenting stakeholder needs, which has already occurred in the scenario.
  • C. Create WBS involves decomposing the project scope into smaller deliverables, which comes after defining the overall scope.

Define Scope

The process of developing a detailed description of the project and product.

  • Elaborates on the project charter and requirements documentation.
  • Results in the project scope statement.
  • Helps prevent scope creep by setting clear boundaries.

Memory trick: Scope's Path: Plan, Collect, Define, WBS, Validate, Control.

More Predictive, Plan-Based Methodologies questions