CSLB C-10 Electrical ContractorEquipment and InstallationMedium

An electrician installs a multiwire branch circuit consisting of two ungrounded conductors and a shared neutral, supplying receptacles in a kitchen. The circuit uses two single-pole circuit breakers without a handle tie or common-trip mechanism. Does this installation comply with NEC 210.4(B)?

  1. ANo, a means must be provided to simultaneously disconnect all ungrounded conductors at the panelboard, such as a handle tie or common-trip breaker.
  2. BYes, single-pole breakers are always acceptable for multiwire branch circuits.
  3. CNo, multiwire branch circuits are prohibited entirely in dwelling units.
  4. DYes, as long as the neutral conductor is oversized.
Show answer & explanation

Correct answer: A. No, a means must be provided to simultaneously disconnect all ungrounded conductors at the panelboard, such as a handle tie or common-trip breaker.

NEC 210.4(B) requires that multiwire branch circuits be provided with a means to simultaneously disconnect all ungrounded conductors at the panelboard, using either identified handle ties or a common multipole breaker, so that the circuit cannot be de-energized on only one leg while the other remains energized.

Why the other options are wrong

  • B. Single-pole breakers without a simultaneous disconnect means do not meet 210.4(B).
  • C. Multiwire branch circuits are permitted in dwellings when properly installed, not prohibited.
  • D. Neutral conductor sizing does not satisfy the simultaneous disconnect requirement.

Multiwire Branch Circuit Disconnect (210.4(B))

Multiwire branch circuits must have a means to simultaneously disconnect all ungrounded conductors at the panelboard where the circuit originates.

  • Handle ties or common-trip breakers satisfy the requirement
  • Prevents energized neutral hazards during single-pole servicing
  • Applies wherever a shared neutral serves two or more ungrounded conductors

Memory trick: 'Tie the handles so both legs die together.'