CompTIA Project+ (PK0-005)Project Management ConceptsMedium

A project manager is reviewing the project schedule and identifies Task A (duration 5 days) must complete before Task B (duration 3 days) can start. Task B must complete before Task C (duration 4 days) can start. Task A starts on Day 1. What is the earliest possible Finish (EF) date for Task C?

  1. ADay 9
  2. BDay 11
  3. CDay 8
  4. DDay 12
Show answer & explanation

Correct answer: D. Day 12

Task A finishes on Day 5 (Day 1 + 5 days - 1 day for start). Task B starts on Day 6 and finishes on Day 8 (Day 6 + 3 days - 1 day). Task C starts on Day 9 and finishes on Day 12 (Day 9 + 4 days - 1 day).

Why the other options are wrong

  • A. Incorrect. This would be if C finished on Day 9 (e.g., started Day 6 and had 4 days duration).
  • B. Incorrect. This would be if C finished on Day 11 (e.g., started Day 8 and had 4 days duration).
  • C. Incorrect. This would be if C started on Day 5 and finished on Day 8.

Earliest Finish (EF)

The earliest date on which an activity can be completed, given its dependencies and durations.

  • Calculated by adding the activity's duration to its Earliest Start (ES) date and subtracting one.
  • A key component of the Critical Path Method (CPM).
  • Used to determine the earliest possible project completion date.

Memory trick: ES + Duration - 1 = EF. Easy math for a schedule path.