CompTIA Project+ (PK0-005)Project Management ConceptsEasy

A project manager is overseeing a complex software development project. The team frequently delivers working software in short iterations and adapts to changing requirements throughout the project lifecycle. Which project management methodology is MOST likely being utilized?

  1. ACritical Path Method (CPM)
  2. BPRINCE2
  3. CAgile
  4. DWaterfall
Show answer & explanation

Correct answer: C. Agile

Agile methodologies are characterized by iterative development, frequent delivery of working software, and adaptability to change, which aligns with the project description.

Why the other options are wrong

  • A. CPM is a scheduling technique, not a full project management methodology.
  • B. PRINCE2 is a structured project management method, but not specifically known for frequent software delivery in short iterations.
  • D. Waterfall is a sequential, linear methodology that does not emphasize frequent delivery or adaptability.

Agile Methodology

An iterative and incremental approach to project management that emphasizes collaboration, self-organizing teams, and continuous delivery of value.

  • Focuses on flexibility and adaptability to change.
  • Delivers working software frequently in short iterations.
  • Values individuals and interactions over processes and tools.

Memory trick: Agile teams move like a nimble fox, quickly adapting to the hunt.

More Project Management Concepts questions