CompTIA Project+ (PK0-005)Project Management ConceptsEasy
A project manager is leading a software development project using the Scrum framework. The team is consistently delivering working software and adapting to changes, but the project manager notices that the team struggles with self-organization and adhering to the Scrum events. Which Scrum role is primarily responsible for coaching the team on Scrum principles and facilitating its effective use?
- AScrum Master
- BProduct Owner
- CProject Sponsor
- DDevelopment Team
Show answer & explanationAnswer & explanation
Correct answer: A. Scrum Master
The Scrum Master is the servant-leader for the Scrum Team, responsible for ensuring Scrum is understood and enacted. This includes coaching the team on self-organization and facilitating Scrum events.
Why the other options are wrong
- B. The Product Owner is responsible for maximizing the value of the product resulting from the work of the Development Team.
- C. The Project Sponsor provides resources and support for the project and is accountable for its success, but not for Scrum framework adherence.
- D. The Development Team is responsible for delivering a potentially releasable Increment of 'Done' product at the end of each Sprint.
Scrum Master Role
A servant-leader for the Scrum Team, responsible for promoting and supporting Scrum as defined in the Scrum Guide. They coach the team on self-organization and facilitate Scrum events.
- Coaches the Development Team in self-organization and cross-functionality.
- Ensures Scrum is understood and enacted.
- Removes impediments to the Development Team's progress.
Memory trick: POSD: Product Owner, Scrum Master, Development Team - each has a specific Job.