A project manager is leading a software development project using the Scrum framework. The team is consistently delivering working software and adapting to changes, but the project manager notices that the team struggles with self-organization and adhering to the Scrum events. Which Scrum role is primarily responsible for coaching the team on Scrum principles and facilitating its effective use?

  1. AScrum Master
  2. BProduct Owner
  3. CProject Sponsor
  4. DDevelopment Team
Show answer & explanation

Correct answer: A. Scrum Master

The Scrum Master is the servant-leader for the Scrum Team, responsible for ensuring Scrum is understood and enacted. This includes coaching the team on self-organization and facilitating Scrum events.

Why the other options are wrong

  • B. The Product Owner is responsible for maximizing the value of the product resulting from the work of the Development Team.
  • C. The Project Sponsor provides resources and support for the project and is accountable for its success, but not for Scrum framework adherence.
  • D. The Development Team is responsible for delivering a potentially releasable Increment of 'Done' product at the end of each Sprint.

Scrum Master Role

A servant-leader for the Scrum Team, responsible for promoting and supporting Scrum as defined in the Scrum Guide. They coach the team on self-organization and facilitate Scrum events.

  • Coaches the Development Team in self-organization and cross-functionality.
  • Ensures Scrum is understood and enacted.
  • Removes impediments to the Development Team's progress.

Memory trick: POSD: Product Owner, Scrum Master, Development Team - each has a specific Job.