CompTIA Project+ (PK0-005)Project Management ConceptsMedium
A project team is developing a new mobile application using an Agile methodology. The product owner frequently provides new user stories and reprioritizes existing ones based on market feedback. Which Agile principle is BEST exemplified by this scenario?
- AWorking software over comprehensive documentation.
- BIndividuals and interactions over processes and tools.
- CCustomer collaboration over contract negotiation.
- DResponding to change over following a plan.
Show answer & explanationAnswer & explanation
Correct answer: D. Responding to change over following a plan.
The frequent reprioritization and addition of user stories based on market feedback directly reflect the Agile principle of valuing adaptability and responsiveness to change over strict adherence to an initial plan.
Why the other options are wrong
- A. This principle prioritizes functional deliverables, but doesn't specifically address the process of accepting new requirements.
- B. While important, this principle focuses on team dynamics, not the ability to adapt to evolving requirements.
- C. Customer collaboration is present, but the core of the scenario is about how changes from that collaboration are handled.
Agile Principle: Respond to Change
One of the four core values of the Agile Manifesto, emphasizing the importance of adapting to evolving requirements and circumstances over rigid adherence to a pre-defined plan.
- Embraces flexibility and adaptability.
- Prioritizes stakeholder feedback and market shifts.
- Allows for continuous improvement and course correction.
Memory trick: I C W R: Individuals, Collaboration, Working, Responding.