CompTIA Project+ (PK0-005)Project Management ConceptsMedium

A project manager is reviewing the project schedule and identifies a task, 'User Acceptance Testing (UAT)', that cannot start until 'Software Development' is 100% complete. Furthermore, 'UAT' must finish before 'Deployment' can begin. What type of dependency is described between 'Software Development' and 'User Acceptance Testing (UAT)'?

  1. AFinish-to-Start (FS)
  2. BFinish-to-Finish (FF)
  3. CStart-to-Start (SS)
  4. DStart-to-Finish (SF)
Show answer & explanation

Correct answer: A. Finish-to-Start (FS)

The statement 'UAT cannot start until Software Development is 100% complete' perfectly describes a Finish-to-Start (FS) dependency, where the successor activity (UAT) can only begin after its predecessor (Software Development) is finished.

Why the other options are wrong

  • B. Finish-to-Finish means the successor activity cannot finish until the predecessor activity has finished.
  • C. Start-to-Start means the successor activity cannot start until the predecessor activity has started.
  • D. Start-to-Finish means the successor activity cannot finish until the predecessor activity has started; this is rarely used.

Finish-to-Start (FS) Dependency

A logical relationship where a successor activity cannot start until a predecessor activity has finished. It is the most common type of dependency.

  • Predecessor must complete before successor begins.
  • Represented as A → B.
  • Forms the basis of critical path calculations.

Memory trick: Activities link up: Start to Start, Finish to Start, Finish to Finish, Start to Finish.