CompTIA Project+ (PK0-005)Project Management ConceptsMedium
A project manager is leading a project to develop a new mobile application. The team is using an Agile methodology, and during a recent Sprint Review, stakeholders expressed concerns that the application's user interface (UI) is not intuitive enough. The Product Owner agrees and wants to prioritize UI improvements in the next Sprint. Which Agile principle is best demonstrated by this scenario?
- ACustomer collaboration over contract negotiation
- BIndividuals and interactions over processes and tools
- CResponding to change over following a plan
- DWorking software over comprehensive documentation
Show answer & explanationAnswer & explanation
Correct answer: C. Responding to change over following a plan
The scenario describes stakeholders providing feedback that leads to a change in priorities for the next Sprint. This direct adaptation to new information and feedback, rather than rigidly adhering to an initial plan, exemplifies the Agile principle of 'Responding to change over following a plan'.
Why the other options are wrong
- A. This principle highlights the importance of working closely with customers throughout the project lifecycle.
- B. This principle emphasizes the importance of human interaction and collaboration within the team.
- D. This principle values delivering functional software frequently over extensive paperwork.
Agile Principle: Responding to Change
One of the twelve principles behind the Agile Manifesto, it states that agile processes harness change for the customer's competitive advantage. This means being able to adapt plans and priorities based on new information and feedback.
- Embraces change as an opportunity, not a problem.
- Allows for flexibility in project direction.
- Contributes to delivering higher customer value.
Memory trick: I Work, Customers Respond to Change.