A project manager is analyzing the critical path for a project. Task A has a duration of 5 days. Task B has a duration of 3 days and can only start after Task A finishes. Task C has a duration of 4 days and can only start after Task B finishes. Task D has a duration of 2 days and can run concurrently with Task B, starting after Task A finishes. What is the earliest finish (EF) date for the project if Task A starts on Day 1?

  1. ADay 14
  2. BDay 10
  3. CDay 12
  4. DDay 8
Show answer & explanation

Correct answer: C. Day 12

Path 1: A (5 days) + B (3 days) + C (4 days) = 5 + 3 + 4 = 12 days. Path 2: A (5 days) + D (2 days) = 5 + 2 = 7 days. The longest path determines the earliest finish for the project, which is 12 days. Since Task A starts on Day 1, the project will finish on Day 12.

Why the other options are wrong

  • A. Incorrect. This would imply a longer critical path than calculated.
  • B. Incorrect. This might be a miscalculation of one of the paths.
  • D. Incorrect. This would be the duration if only Task A and B were considered or if the critical path was shorter.

Earliest Finish (EF)

The earliest date on which an activity can be completed, given the network logic and activity durations. For a project, it's the EF of the last activity on the critical path.

  • Determined by forward pass calculation.
  • Calculated as Early Start + Duration.
  • The project's EF is the EF of the last activity on the critical path.

Memory trick: CPM finds the longest path to the finish line.