CompTIA Project+ (PK0-005)Project Management ConceptsMedium

A project manager is reviewing the project schedule and identifies Task A, which has a duration of 3 days. Task B, with a duration of 5 days, cannot start until Task A is 50% complete. What type of logical relationship exists between Task A and Task B?

  1. AFinish-to-Start (FS)
  2. BStart-to-Finish (SF)
  3. CStart-to-Start (SS)
  4. DFinish-to-Finish (FF)
Show answer & explanation

Correct answer: C. Start-to-Start (SS)

The relationship states that Task B 'cannot start until Task A is 50% complete'. This means the start of Task B is dependent on the start of Task A, with a lag or lead. Since Task B starts after Task A has started (and progressed to 50%), it's a Start-to-Start (SS) relationship with a lead or lag.

Why the other options are wrong

  • A. Finish-to-Start (FS) means one task must finish before the next can start.
  • B. Start-to-Finish (SF) means one task cannot finish until another task has started.
  • D. Finish-to-Finish (FF) means one task cannot finish until another task has finished.

Start-to-Start (SS) Dependency

A logical relationship where the successor activity cannot start until the predecessor activity has started. It can include a lag or lead time.

  • Successor starts after predecessor starts.
  • Often used when tasks can be partially parallel.
  • Example: 'Pour foundation' can start when 'Excavate site' starts, but not necessarily immediately.

Memory trick: FS, SS, FF, SF: Friends Start, Sisters Finish, Fathers Start, Sons Finish.