CompTIA Project+ (PK0-005)Project Management ConceptsHard

A project manager is overseeing a software development project where the team is frequently interrupted by urgent requests from stakeholders for new features, causing scope creep and missed deadlines. Which project role is primarily responsible for protecting the team from external interference and ensuring they remain focused on the current sprint goals?

  1. AProject Sponsor
  2. BDevelopment Team Member
  3. CScrum Master
  4. DProduct Owner
Show answer & explanation

Correct answer: C. Scrum Master

The Scrum Master is responsible for facilitating Scrum events, coaching the team, and most importantly, removing impediments and protecting the Development Team from external interference and distractions, enabling them to focus on the Sprint Goal.

Why the other options are wrong

  • A. The Project Sponsor provides resources and high-level guidance but doesn't typically shield the team from day-to-day interruptions.
  • B. Development Team Members focus on building the product increment and are the ones being protected, not the protectors in this context.
  • D. The Product Owner is responsible for maximizing the value of the product and managing the Product Backlog, but not for shielding the team from external interruptions.

Scrum Master Role

The servant-leader for the Scrum Team, responsible for ensuring Scrum is understood and enacted, and for protecting the Development Team.

  • Facilitates Scrum events.
  • Removes impediments for the Development Team.
  • Coaches the team and organization on Scrum practices.

Memory trick: Scrum Master shields the team like a master guardian.