CSLB Law & Business ExamContract Requirements and ExecutionMedium

A contractor has a homeowner sign a home improvement contract for a bathroom remodel. Under California law, when must the contractor provide the homeowner with a completed copy of the signed contract?

  1. AOnly upon completion of the work
  2. BWithin 10 days after the contract is signed
  3. COnly if the homeowner requests it in writing
  4. DAt the time the homeowner signs the contract
Show answer & explanation

Correct answer: D. At the time the homeowner signs the contract

California law requires that the homeowner receive a copy of the fully completed contract at the time of signing. This immediate delivery ensures the homeowner has a record of the exact terms agreed upon, including price, scope, and disclosures.

Why the other options are wrong

  • A. Waiting until job completion is far too late and violates the law.
  • B. Delaying delivery by 10 days does not meet the immediate delivery requirement.
  • C. The homeowner should not have to request a copy; it must be provided automatically.

Contract Copy at Signing

Homeowners must receive a fully completed copy of the home improvement contract at the time they sign it.

  • Immediate delivery required
  • No waiting for request or job completion
  • Protects homeowner's record of agreed terms

Memory trick: Sign it, get it — same moment

More Contract Requirements and Execution questions