CSLB Law & Business ExamContract Requirements and ExecutionHard

A home improvement contract specifies a start date of March 1. Due to a permit delay, the contractor is unable to begin work until March 20. Under California law, what is the contractor's obligation regarding this delay?

  1. AThe contractor must automatically reduce the contract price by 10% for each week of delay
  2. BNo action is required since minor scheduling delays are presumed acceptable
  3. CThe contractor must notify the homeowner in writing of the reason for the delay and provide a revised start date
  4. DThe contractor must void the contract and require the homeowner to rebid the project
Show answer & explanation

Correct answer: C. The contractor must notify the homeowner in writing of the reason for the delay and provide a revised start date

California law requires that if a contractor cannot begin or complete work within the timeframe stated in the contract, the contractor must notify the homeowner in writing of the reason for the delay and provide a new start or completion date, preserving the homeowner's ability to make informed decisions about the project.

Why the other options are wrong

  • A. There is no automatic price-reduction penalty required by law for delays.
  • B. Delays are not simply presumed acceptable without notice.
  • D. A delay does not automatically void the contract or require rebidding.

Notice of Schedule Delay

If a contractor cannot meet the stated start or completion date, California law requires written notice to the homeowner explaining the delay and providing a new date.

  • Delay must be communicated in writing
  • Must include reason and new date
  • Protects homeowner's right to make informed decisions

Memory trick: Late start? Send a note, with a new date to quote.

More Contract Requirements and Execution questions