Step2Study
ContractorC-39100% Free

CSLB C-39 Roofing Contractor

Practice bank
207 Qs
Real exam
110 Qs
Time limit
210 min
Passing
~72% (scaled; CSLB/PSI)

Exam blueprint

Estimating and Planning
20%
Steep-Slope Roofing
25%
Low-Slope Roofing
25%
Flashing, Ventilation and Insulation
15%
Safety and Repair
15%

Practice

Untimed · instant feedback · 4 practice tests of 90 questions

Questions per test

Custom practice

Flashcard on every question Mental map when you miss

Exam simulation

4 timed tests · 110 questions each · 210 min · pass 72% · 207 questions in the bank

+50 XP per test · +100 XP for a pass

Random simulation (weighted by domain)

Everything is open to everyone. Create a free account to save scores, XP, badges and get progress emails.

Free study resources

All resources →

Part of a learning path

Study with friends

Challenge a friend to beat your score.

CSLB C-39 Roofing Contractor practice test questions

Sample questions from the 207-question bank, with answers and explanations.

All questions
  1. 1. Per California Building Code provisions governing asphalt shingle roof underlayment, a double layer of underlayment is required for roof slopes within which range?

    Estimating and Planning

    • A. Greater than 6:12
    • B. 2:12 up to less than 4:12
    • C. 4:12 up to 6:12
    • D. 0:12 up to 2:12
    Show answer

    B. 2:12 up to less than 4:12

    Asphalt shingles are only approved for slopes of 2:12 or greater, and slopes between 2:12 and less than 4:12 require a double layer of underlayment (or an approved cap sheet system) due to increased water infiltration risk on low slopes.

  2. 2. A roofer is flashing a skylight installed on a composition shingle roof. Which flashing component is installed last, at the top (upslope) edge of the skylight curb, overlapping the roofing material above it?

    Flashing, Ventilation and Insulation

    • A. Head flashing
    • B. Step flashing
    • C. Counter flashing
    • D. Apron (bottom) flashing
    Show answer

    A. Head flashing

    Skylight flashing follows a shingle-style, water-shedding sequence: apron flashing goes in first at the bottom, then step flashing up the sides, and finally head flashing is installed at the top, tucked under the upslope shingles so water sheds over it away from the curb.

  3. 3. A roof has 14 plumbing vent stack penetrations requiring pipe flashing boots. The estimator adds 10% extra to cover potential damage during installation, and boots are sold in packs of 6. How many packs must be purchased?

    Estimating and Planning

    • A. 5 packs
    • B. 4 packs
    • C. 2 packs
    • D. 3 packs
    Show answer

    D. 3 packs

    Add 10% to the 14 penetrations: 14 × 1.10 = 15.4, rounded up to 16 boots needed. Divide by pack size: 16 ÷ 6 = 2.67, rounded up to 3 packs since partial packs cannot be purchased.

  4. 4. A crew is installing a 4-ply BUR system on a 1,200 square foot roof section, requiring 3 interply asphalt moppings at a rate of 23 pounds per square (100 sq ft). How many total pounds of asphalt are needed for the interply moppings?

    Low-Slope Roofing

    • A. 1,104 pounds
    • B. 552 pounds
    • C. 276 pounds
    • D. 828 pounds
    Show answer

    D. 828 pounds

    1,200 sq ft = 12 squares. Asphalt per mopping = 23 lb/square × 12 squares = 276 lb. Total for 3 moppings = 276 × 3 = 828 pounds.

  5. 5. A hip roof has a common rafter run of 15 feet with a 6:12 slope. Using the standard rafter table hip/valley factor of 16.97 inches of hip length per foot of common rafter run, what is the total hip rafter length?

    Estimating and Planning

    • A. 18.75 feet
    • B. 21.2 feet
    • C. 17.0 feet
    • D. 23.5 feet
    Show answer

    B. 21.2 feet

    The hip rafter factor already accounts for the diagonal geometry of the hip in three dimensions. Multiplying the common rafter run by the factor and converting to feet: 15 ft × 16.97 in/ft = 254.55 inches, then 254.55 ÷ 12 = 21.2 feet.

  6. 6. A hip roof has a ridge line of 36 linear feet and four hips measuring 14 linear feet each. Ridge cap shingle bundles cover 25 linear feet per bundle. Applying a 10% waste factor, how many bundles of ridge cap should be ordered?

    Estimating and Planning

    • A. 4 bundles
    • B. 6 bundles
    • C. 5 bundles
    • D. 7 bundles
    Show answer

    C. 5 bundles

    Total linear footage = 36 ft ridge + (4 × 14 ft) hips = 36 + 56 = 92 ft. With 10% waste: 92 × 1.10 = 101.2 ft. Bundles needed = 101.2 ÷ 25 = 4.05, rounding up to 5 bundles.

  7. 7. A synthetic underlayment roll covers 10 squares (1,000 sq ft) net after overlap. The total roof area is 32 squares. Applying the standard 10% waste factor for laps and cuts, how many rolls should be ordered?

    Estimating and Planning

    • A. 6 rolls
    • B. 4 rolls
    • C. 3 rolls
    • D. 5 rolls
    Show answer

    B. 4 rolls

    32 squares × 1.10 waste factor = 35.2 squares needed. 35.2 ÷ 10 squares/roll = 3.52, which rounds up to 4 rolls.

  8. 8. A two-person roofing crew can install 2.5 squares per hour on a straightforward gable roof. The job totals 32 squares of shingles. Based solely on the installation rate, how many labor hours should the estimator budget to complete the shingle installation?

    Estimating and Planning

    • A. 11.2 hours
    • B. 10.5 hours
    • C. 14.4 hours
    • D. 12.8 hours
    Show answer

    D. 12.8 hours

    Divide the total squares by the crew's installation rate: 32 ÷ 2.5 = 12.8 labor hours.

  9. 9. A roofer is installing an open metal valley on an asphalt shingle roof. Per standard practice, what should be done regarding the shingles adjacent to the valley?

    Steep-Slope Roofing

    • A. Shingles should be nailed directly through the center of the valley metal for maximum hold
    • B. Shingles should be installed with a 1-inch gap on only one side of the valley
    • C. Shingles should be trimmed to expose a clear metal channel, with edges clipped and sealed with roofing cement
    • D. Shingles should overlap completely across the valley with no exposed metal visible
    Show answer

    C. Shingles should be trimmed to expose a clear metal channel, with edges clipped and sealed with roofing cement

    In an open valley, shingles on both sides are trimmed back to expose a clear metal channel (typically widening from about 3 inches at the ridge to wider at the eave), with the upper corner of each shingle clipped and embedded in roofing cement to direct water flow without trapping debris.

  10. 10. A roof valley measures 80 linear feet. Self-adhered membrane rolls are 36 inches wide by 36 feet long, and code requires a minimum 6-inch (0.5-foot) end-lap overlap between consecutive rolls along the valley run. How many rolls are needed to cover this single valley?

    Estimating and Planning

    • A. 2 rolls
    • B. 4 rolls
    • C. 5 rolls
    • D. 3 rolls
    Show answer

    D. 3 rolls

    Each roll provides 36 ft of length but loses 0.5 ft to the overlap with the next roll, giving 35.5 ft of effective coverage per roll. Rolls needed = 80 ÷ 35.5 = 2.25, rounded up to 3 full rolls.

  11. 11. A technician installs step flashing along a shingle roof/sidewall intersection. Each individual step flashing piece must extend a minimum of how far up the wall and overlap the piece below it by how much?

    Flashing, Ventilation and Insulation

    • A. 2 inches up the wall, 1 inch overlap
    • B. 6 inches up the wall, 3 inches overlap
    • C. 8 inches up the wall, 4 inches overlap
    • D. 4 inches up the wall, 2 inches overlap
    Show answer

    D. 4 inches up the wall, 2 inches overlap

    Code requires each step flashing shingle to extend a minimum of 4 inches onto the wall surface and lap the piece below by at least 2 inches, ensuring continuous water shedding down the wall and onto the roof plane.

  12. 12. A roofing contractor measures a house and finds the total roof surface area (all planes combined) is 2,450 square feet. Rounding up to the nearest whole square with no waste added, how many squares should be listed on the material order?

    Estimating and Planning

    • A. 25 squares
    • B. 24.5 squares
    • C. 24 squares
    • D. 26 squares
    Show answer

    A. 25 squares

    One roofing square equals 100 square feet. 2,450 ÷ 100 = 24.5 squares, and material is always rounded UP to the next whole square, giving 25 squares.

  13. 13. During a roof drainage inspection, a technician checks the strainer/dome on a primary roof drain. Per the California Plumbing Code, at minimum how many inches must the strainer extend above the roof surface immediately surrounding the drain?

    Low-Slope Roofing

    • A. 4 inches
    • B. 8 inches
    • C. 2 inches
    • D. 6 inches
    Show answer

    A. 4 inches

    The California Plumbing Code requires roof drain strainers to extend a minimum of 4 inches above the surface of the roof immediately adjacent to the strainer, ensuring debris does not block water flow into the drain.

  14. 14. A roofing contractor is installing tapered insulation to create positive drainage on a low-slope BUR roof. The specified taper is 1/4 inch per foot, sloping from a roof drain at the low point to a high point 40 feet away. If the insulation thickness at the drain is 1.5 inches, what minimum insulation thickness is required at the high point?

    Low-Slope Roofing

    • A. 13 inches
    • B. 11.5 inches
    • C. 10 inches
    • D. 15.5 inches
    Show answer

    B. 11.5 inches

    Total rise = 1/4 in/ft × 40 ft = 10 inches. Adding this to the starting thickness at the drain (1.5 in) gives 1.5 + 10 = 11.5 inches at the high point.

  15. 15. A technician is specifying a PVC single-ply membrane for a re-roof over an existing modified bitumen roof. Why is direct contact between PVC membrane and asphalt-based products typically avoided?

    Low-Slope Roofing

    • A. Asphalt will bleach the PVC membrane white over time
    • B. Plasticizers in PVC can migrate and react with asphalt, causing membrane degradation
    • C. Asphalt will chemically bond too strongly to PVC, making future repairs impossible
    • D. PVC cannot be heat-welded once exposed to asphalt fumes
    Show answer

    B. Plasticizers in PVC can migrate and react with asphalt, causing membrane degradation

    PVC membranes contain plasticizers that can migrate when in direct contact with asphalt-based materials, leading to embrittlement, discoloration, and premature failure of the membrane. A compatible separator or cover board is required between PVC and asphaltic substrates.

  16. 16. A rectangular building measures 30 feet wide (eave to eave) and 50 feet long, with a roof slope of 5:12. Using a rafter length factor of 1.083 for a 5:12 slope, what is the total roof surface area (both roof planes combined), in square feet?

    Estimating and Planning

    • A. 1,500 square feet
    • B. 1,624.5 square feet
    • C. 1,687 square feet
    • D. 1,562 square feet
    Show answer

    B. 1,624.5 square feet

    The horizontal run to the ridge is half the building width: 30 ÷ 2 = 15 feet. Rafter length equals run × slope factor: 15 × 1.083 = 16.245 feet. Each roof plane's area equals rafter length × building length: 16.245 × 50 = 812.25 sq ft. Doubling for both planes: 812.25 × 2 = 1,624.5 square feet.

  17. 17. A contractor installs R-19 fiberglass batt insulation (designed for a 6-1/4 inch cavity) into a 2×4 wall cavity that is only 3-1/2 inches deep. What is the most accurate outcome of this installation?

    Flashing, Ventilation and Insulation

    • A. The batt will still perform at its full rated R-19 value since the material itself hasn't changed
    • B. The compressed batt's effective R-value will be lower than R-19 because compression reduces trapped air volume
    • C. The R-value will increase because compression makes the fibers denser and more effective
    • D. Compression has no effect on thermal performance, only on vapor permeability
    Show answer

    B. The compressed batt's effective R-value will be lower than R-19 because compression reduces trapped air volume

    Fiberglass batt insulation relies on trapped air pockets between fibers for its R-value rating. Compressing a batt designed for 6-1/4 inches into a shallower 3-1/2 inch cavity reduces the air space, resulting in a lower effective R-value (an R-19 batt compressed this way typically performs closer to R-13).

  18. 18. A homeowner asks a contractor to add gable end vents to an attic that already has a continuous ridge vent and soffit vents. Why should the contractor advise against combining gable vents with a ridge vent system?

    Flashing, Ventilation and Insulation

    • A. Gable vents block sunlight needed for the ridge vent's thermal draw to function
    • B. The gable vents will short-circuit the airflow by pulling air from the nearest opening instead of drawing it from the soffits across the full attic
    • C. Building code prohibits any attic from having more than one type of vent
    • D. Gable vents will overpressurize the attic and cause structural damage to the ridge
    Show answer

    B. The gable vents will short-circuit the airflow by pulling air from the nearest opening instead of drawing it from the soffits across the full attic

    When gable vents are combined with a ridge vent, wind and thermal draw can cause air to be pulled in and out through the nearby gable vent rather than traveling the intended path from the soffits to the ridge, creating a 'short-circuit' that leaves large portions of the attic poorly ventilated.

  19. 19. A hip roof has a flat plan (footprint) area of 2,400 square feet and a slope of 8:12. Using a standard roof area factor table, the area factor for an 8:12 hip roof is 1.20. What is the actual roof surface area, expressed in roofing squares?

    Estimating and Planning

    • A. 26.4 squares
    • B. 28.8 squares
    • C. 24 squares
    • D. 31.2 squares
    Show answer

    B. 28.8 squares

    Multiply the flat plan area by the area factor: 2,400 × 1.20 = 2,880 square feet. Convert to squares: 2,880 ÷ 100 = 28.8 squares.

  20. 20. A ballasted EPDM roof system is being installed in a low wind exposure zone where code requires a minimum ballast rate of 10 lb per square foot. The roof area is 6,000 sq ft. How many tons of ballast are required?

    Low-Slope Roofing

    • A. 20 tons
    • B. 30 tons
    • C. 40 tons
    • D. 15 tons
    Show answer

    B. 30 tons

    6,000 sq ft × 10 lb/sq ft = 60,000 lb. Converting to tons: 60,000 ÷ 2,000 lb/ton = 30 tons of ballast required.

  21. 21. A standard three-tab asphalt shingle measures 12 inches by 36 inches. What is the standard weather exposure used when installing these shingles on a typical steep-slope roof?

    Steep-Slope Roofing

    • A. 6 inches
    • B. 5 inches
    • C. 7 inches
    • D. 4 inches
    Show answer

    B. 5 inches

    A standard 12x36 three-tab shingle has three 12-inch-wide tabs, and the standard weather exposure recommended by manufacturers and referenced in roofing codes is 5 inches, leaving a 7-inch headlap for weatherproofing.

  22. 22. A contractor is installing closed-cell spray polyurethane foam directly against the underside of the roof sheathing to create a conditioned, unvented attic assembly. According to standard building practice for this assembly type, what is required regarding attic ventilation?

    Flashing, Ventilation and Insulation

    • A. Ventilation requirements double because spray foam traps excess moisture in the attic
    • B. Gable vents alone are sufficient since ridge vents would compromise the foam seal
    • C. No soffit or ridge ventilation is required because the roof deck itself becomes part of the building's thermal and air barrier
    • D. Standard 1/150 ventilation must still be provided through soffit and ridge vents
    Show answer

    C. No soffit or ridge ventilation is required because the roof deck itself becomes part of the building's thermal and air barrier

    When closed-cell spray foam is applied directly to the roof deck, the attic becomes part of the conditioned building envelope (an 'unvented attic assembly'). Because the foam acts as both insulation and an air/vapor barrier at the roof deck, the traditional soffit-to-ridge ventilation pathway is unnecessary and is typically omitted.

  23. 23. A roofer is installing a fully adhered EPDM membrane and applies EPDM splice adhesive to both the membrane and flashing surfaces before joining them. Per typical manufacturer instructions, what must the applicator do after coating both surfaces and before pressing them together?

    Low-Slope Roofing

    • A. Immediately press the surfaces together while the adhesive is still wet
    • B. Wait until the adhesive is completely dry and hard before joining the surfaces
    • C. Apply a second coat of adhesive over the first before it dries at all
    • D. Allow the adhesive to flash off until it is tacky but not wet, forming no strings when touched
    Show answer

    D. Allow the adhesive to flash off until it is tacky but not wet, forming no strings when touched

    EPDM splice adhesive (contact adhesive) must flash off to a tacky, string-free state before the two surfaces are mated; bonding too wet traps solvent and weakens the bond, while waiting until fully dry prevents adhesion altogether.

  24. 24. A roof requires drip edge along 180 linear feet of eaves and 140 linear feet of rakes, for a combined edge length of 320 feet. Drip edge stock comes in 10-foot pieces, and the estimator adds a standard 5% waste allowance for laps and cuts. How many pieces of drip edge should be ordered?

    Estimating and Planning

    • A. 34 pieces
    • B. 32 pieces
    • C. 33 pieces
    • D. 36 pieces
    Show answer

    A. 34 pieces

    Adding 5% waste to 320 feet gives 320 × 1.05 = 336 linear feet. Dividing by the 10-foot piece length gives 336 ÷ 10 = 33.6, which rounds up to 34 whole pieces since partial pieces cannot be ordered.

  25. 25. A common rafter runs 14 feet horizontally to the ridge with a rise of 8 feet over that run, and extends an additional 2-foot horizontal overhang beyond the exterior wall (total horizontal run of 16 feet) at the same consistent slope. Using the Pythagorean theorem, what is the total rafter length including the overhang, to the nearest tenth of a foot?

    Estimating and Planning

    • A. 16.1 feet
    • B. 19.6 feet
    • C. 17.2 feet
    • D. 18.4 feet
    Show answer

    D. 18.4 feet

    The slope ratio is 8÷14 = 0.5714 ft rise per ft run. Over the full 16-ft run, total rise = 0.5714 × 16 = 9.14 ft. Rafter length = √(16² + 9.14²) = √(256 + 83.6) = √339.6 ≈ 18.4 feet.

CSLB C-39 Roofing Contractor flashcards

Tap a card to flip it. 193 flashcards in the full deck.

  • Double Underlayment Requirement

    Flip card

    Building code requires a double layer of underlayment on low-slope asphalt shingle roofs (2:12 to under 4:12) to compensate for slower water runoff.

    • Asphalt shingles require minimum 2:12 slope
    • 2:12 to <4:12 requires double underlayment application
    • 4:12 and above only requires standard single-layer underlayment
    Study this card →
  • Skylight Flashing Sequence

    Flip card

    Skylight flashing is installed shingle-fashion: apron (bottom) first, step flashing up the sides, and head flashing last at the top under upslope shingles.

    • Apron flashing = bottom, installed first
    • Step flashing = sides, interwoven with shingles
    • Head flashing = top, installed last, under upslope shingles
    Study this card →
  • Pipe Boot Takeoff

    Flip card

    Pipe flashing boot quantities are calculated by counting penetrations, adding a waste/spare allowance, then dividing by the pack size sold.

    • Add a spare percentage before dividing by pack size.
    • Always round up both the boot count and the pack count.
    • Pack sizes vary by manufacturer, commonly sold in sets of 6.
    Study this card →
  • BUR Asphalt Mopping Rate Calculation

    Flip card

    Built-up roofing requires interply asphalt moppings, typically applied around 20-25 lb per square, and total asphalt needed scales with area and number of moppings.

    • 1 square = 100 sq ft
    • Total lbs = rate × squares × number of moppings
    • Standard interply rate: ~20-25 lb/square
    Study this card →
  • Hip Rafter Length via Slope Factor Table

    Flip card

    Hip and valley rafters are longer than common rafters for the same run because they travel diagonally in three dimensions; rafter tables provide a per-foot-of-run factor to calculate their true length.

    • Hip/valley factor is always greater than the common rafter factor for the same pitch
    • Multiply common rafter run by the hip factor to get length in inches
    • Divide by 12 to convert the result to feet
    Study this card →
  • Ridge Cap Takeoff

    Flip card

    Ridge cap material quantities are determined by summing all ridge and hip linear footage, applying a waste factor, then dividing by bundle coverage.

    • Add ridge length plus all hip lengths together
    • Apply standard waste factor (commonly 10%)
    • Divide total adjusted footage by bundle coverage and round up
    Study this card →
  • Underlayment Roll Coverage

    Flip card

    Underlayment rolls are rated for net coverage after overlap; waste factors must be added to account for laps, valleys, and cutting.

    • Coverage is stated per roll after overlap allowance
    • Apply 10% waste factor as standard estimating practice
    • Always round rolls up to whole units
    Study this card →
  • Labor Hour Estimating

    Flip card

    Labor hours for a roofing job are estimated by dividing the total roofing squares by the crew's installation production rate per hour.

    • Labor hours = total squares ÷ squares installed per hour.
    • Production rates vary by roof complexity and crew size.
    • Estimators often add buffer time for tear-off, cleanup, and complexity.
    Study this card →
  • Open Valley Flashing

    Flip card

    A valley design where metal flashing is exposed and shingles are trimmed back on both sides to create a clear water channel.

    • Metal channel widens toward the eave
    • Shingle corners clipped and sealed with cement
    • No nails placed within the exposed metal area
    Study this card →
  • Membrane Roll Overlap Takeoff

    Flip card

    When calculating linear roll coverage with end-lap overlaps, subtract the overlap distance from the roll length to find effective coverage, then divide the total run by that effective length.

    • Effective coverage = roll length minus overlap
    • Always round up partial rolls to full rolls
    • Applies to valley membranes, ice barriers, and similar linear runs
    Study this card →
  • Step Flashing Dimensions

    Flip card

    Step flashing pieces must rise at least 4 inches up the sidewall and lap the previous piece by at least 2 inches to prevent water bypass.

    • Installed with each course of shingles, not as one long strip.
    • Minimum 4-inch wall leg per code.
    • Minimum 2-inch overlap between successive pieces.
    Study this card →
  • Roofing Square

    Flip card

    A roofing square is a unit of measure equal to 100 square feet of roof surface, used to standardize material takeoff.

    • 1 square = 100 sq ft
    • Always divide total area by 100 to find squares
    • Round up to the next whole square when ordering
    Study this card →
  • Roof Drain Strainer Height

    Flip card

    The minimum height (4 inches) that a roof drain strainer dome must extend above the adjacent roof surface per the California Plumbing Code, to prevent debris blockage.

    • CPC requires minimum 4-inch strainer height
    • Prevents leaves/debris from clogging the drain
    • Applies to primary roof drains on low-slope roofs
    Study this card →
  • Tapered Insulation Slope Calculation

    Flip card

    Tapered insulation boards are manufactured to create a designed slope toward drains by increasing thickness at a fixed rate per foot of horizontal run.

    • Rise = slope rate (in/ft) × horizontal distance (ft)
    • Final thickness = starting thickness + total rise
    • Common taper rates are 1/8, 1/4, and 1/2 inch per foot
    Study this card →
  • PVC-Asphalt Incompatibility

    Flip card

    PVC membranes contain plasticizers that migrate when in contact with asphalt products, causing membrane embrittlement and failure.

    • Requires separator sheet or cover board
    • Common issue in re-roofing over BUR/mod bit
    • Manufacturers specify compatible barriers
    Study this card →
  • Gable Roof Area from Ridge/Eave Dimensions

    Flip card

    Total gable roof area is found by computing the sloped rafter length from the run and slope factor, then multiplying by building length and doubling for both roof planes.

    • Run to ridge equals half the building width.
    • Rafter length = run × slope factor from a rafter table.
    • Multiply rafter length by building length, then double for two planes.
    Study this card →
  • Insulation Compression Effect

    Flip card

    Fiberglass batt R-values are based on installation at full designed thickness; compressing batts into shallower cavities reduces trapped air and lowers effective R-value.

    • R-value depends on trapped air volume
    • Compressed batts underperform their rating
    • R-19 compressed to 3.5" often performs near R-13
    Study this card →
  • Vent Short-Circuiting

    Flip card

    Combining gable vents with a ridge vent system can cause air to bypass the soffit-to-ridge airflow path, reducing overall attic ventilation effectiveness.

    • Air takes the path of least resistance
    • Nearby gable vent can short-circuit ridge vent draw
    • Best practice: use one consistent exhaust/intake system
    Study this card →
  • Hip Roof Area Factor

    Flip card

    A multiplier from a standard roof area factor table converts a flat plan (footprint) area into actual sloped roof surface area for a given slope and roof type.

    • Multiply footprint area by the slope's area factor.
    • Factors are typically found in rafter/area tables by slope ratio.
    • Convert final square footage to roofing squares by dividing by 100.
    Study this card →
  • Ballast Weight Calculation

    Flip card

    The total weight of loose ballast (typically river rock) required on a ballasted single-ply roof, calculated by multiplying roof area by the code-required ballast rate per square foot.

    • Common minimum rate: 10 lb/sq ft in low wind zones
    • Higher wind exposure zones require heavier ballast rates
    • 1 ton = 2,000 lb
    Study this card →
  • Standard Shingle Exposure

    Flip card

    The portion of a shingle left uncovered (visible) after installation, which determines headlap coverage.

    • Standard 3-tab shingle: 12in x 36in, 5in exposure
    • Exposure + headlap = shingle length minus overlap
    • Manufacturer specs always govern actual exposure
    Study this card →
  • Unvented Conditioned Attic Assembly

    Flip card

    Applying closed-cell spray foam directly to roof sheathing creates a sealed, conditioned attic that becomes part of the building envelope, eliminating the need for soffit/ridge ventilation.

    • Foam applied directly to underside of roof deck
    • Attic becomes part of conditioned space
    • Standard 1/150 or 1/300 ventilation not required
    Study this card →
  • EPDM Splice Adhesive Flash-Off

    Flip card

    A contact adhesive used to bond EPDM seams that must partially dry (flash off) to a tacky, non-stringy state before the two coated surfaces are pressed together.

    • Contact adhesives bond best when tacky, not wet or fully dry
    • Test by touching with a dry finger — no strings or transfer means ready
    • Roll the seam after bonding to ensure full contact
    Study this card →
  • Drip Edge Takeoff

    Flip card

    Drip edge quantities are calculated from total eave and rake footage plus a waste allowance, then divided by stock piece length and rounded up.

    • Combine eave and rake linear footage
    • Apply standard waste percentage (commonly 5%)
    • Round the final piece count up to the next whole piece
    Study this card →

Questions are original practice items written to match the published exam objectives. Step2Study is not affiliated with or endorsed by any certification body.