Professional Scrum Master I (PSM I)Scrum FrameworkMedium

A Scrum Team has noticed a recurring pattern where, even after completing all Product Backlog Items planned for a Sprint, the Increment often contains minor bugs or inconsistencies that require immediate fixes. This leads to rework and delays in delivering true value. Which Scrum artifact's commitment is most likely being insufficiently upheld?

  1. ASprint Goal
  2. BDefinition of Done
  3. CProduct Backlog
  4. DProduct Goal
Show answer & explanation

Correct answer: B. Definition of Done

The Definition of Done is a formal description of the state of the Increment when it meets the quality measures required for the product. If the Increment contains bugs or inconsistencies, it means the Increment is not truly 'Done' according to a sufficient quality standard, indicating that the Definition of Done is not being fully upheld or is insufficient.

Why the other options are wrong

  • A. The Sprint Goal is the objective for the Sprint; while bugs can prevent meeting it, the root cause of 'bugs or inconsistencies' is typically a quality issue defined by DoD.
  • C. The Product Backlog lists items to be built; its content doesn't directly cause bugs in completed work, but the quality standards for completion do.
  • D. The Product Goal is the long-term objective; bugs in an Increment are about quality of individual items, not the overall goal.

Definition of Done as Quality Commitment

The Definition of Done is the formal description of the state of the Increment when it meets the quality measures required for the product. It ensures transparency and quality.

  • A formal agreement by the Scrum Team.
  • Ensures transparency and quality for the Increment.
  • Increases confidence in what is 'Done'.

Memory trick: Artifacts are tied to commitments.