Professional Scrum Master I (PSM I)Scrum FrameworkHard

A Scrum Master is facilitating a Sprint Retrospective. The Developers suggest implementing a new automated testing tool to improve the quality of their code. They agree on a specific action plan to integrate this tool in the next Sprint. What artifact would this improvement plan typically be added to, to ensure its execution and transparency?

  1. AA separate 'Improvements Log' maintained by the Scrum Master.
  2. BThe Sprint Backlog for the upcoming Sprint.
  3. CThe Product Backlog as a high-priority item.
  4. DThe Definition of Done to ensure future quality.
Show answer & explanation

Correct answer: B. The Sprint Backlog for the upcoming Sprint.

Improvements identified during the Sprint Retrospective, especially those with a concrete action plan for the next Sprint, are often added to the Sprint Backlog. This makes them visible, transparent, and ensures the Developers allocate time to implement them alongside other Product Backlog Items.

Why the other options are wrong

  • A. Maintaining a separate 'Improvements Log' by the Scrum Master makes the improvement less transparent to the Developers and Product Owner about its execution and priority compared to being in the Sprint Backlog.
  • C. While it could conceptually be a Product Backlog item, placing it directly into the Product Backlog might imply it's a product feature, and it might not get immediate attention if other business value items are higher. It's more directly related to the *how* of the Sprint.
  • D. The Definition of Done defines the quality standard for the Increment. While the *outcome* of using the tool might improve quality, the *action plan* to implement the tool itself isn't a DoD entry.

Retrospective Improvements

Improvements identified during the Sprint Retrospective should be implemented as soon as possible. Often, they are added to the Sprint Backlog of the upcoming Sprint to ensure they are addressed.

  • Focus on actionable improvements.
  • One or two key improvements are often selected.
  • Adding to Sprint Backlog ensures transparency and allocation of effort.

Memory trick: Retro's Best Go to Sprint's Test.