Master Electrician Exam (NEC)Services, Feeders, and Branch CircuitsEasy

A master electrician is installing a new 200A, 120/240V single-phase service for a dwelling unit. The service entrance conductors are 3/0 AWG copper. What is the minimum size required for the main bonding jumper if it is a wire type?

  1. A1/0 AWG copper
  2. B2 AWG copper
  3. C6 AWG copper
  4. D4 AWG copper
Show answer & explanation

Correct answer: B. 2 AWG copper

NEC Table 250.102(C)(1) specifies the size of the supply-side bonding jumper or main bonding jumper based on the largest ungrounded service-entrance conductor. For 3/0 AWG copper service conductors, the minimum size for the main bonding jumper is 2 AWG copper.

Why the other options are wrong

  • A. This size is larger than required by NEC Table 250.102(C)(1), but not the minimum.
  • C. This size is too small according to NEC Table 250.102(C)(1).
  • D. This size is too small according to NEC Table 250.102(C)(1).

Main Bonding Jumper Sizing (Wire Type)

The main bonding jumper (MBJ) is a conductor that connects the equipment grounding conductor(s) and the service-disconnect enclosure to the grounded conductor of the service.

  • Sized based on the largest ungrounded service-entrance conductor.
  • Refer to NEC Table 250.102(C)(1) for sizing.
  • Ensures a low-impedance path for ground-fault current.

Memory trick: Bonding bridges the gap for safety.