CSLB C-33 Painting & DecoratingPlanning and EstimatingMedium

A painting contractor is preparing an estimate for a residential repaint project. The client has requested an 'allowance' of $1,500 for decorative faux finishes in the dining room. How should the contractor incorporate this allowance into the bid?

  1. AAdd the $1,500 to the total estimated direct costs, then apply the standard overhead and profit percentages to the new total.
  2. BExclude it from the base bid and present it as a separate, optional cost.
  3. CEstimate the actual cost of the faux finish work, then add a 20% contingency to the $1,500 allowance.
  4. DInclude the $1,500 directly in the total bid amount, without applying overhead or profit to it.
Show answer & explanation

Correct answer: A. Add the $1,500 to the total estimated direct costs, then apply the standard overhead and profit percentages to the new total.

An allowance is a specific amount set aside in the contract for an item not yet fully defined. Contractors generally treat allowances as a direct cost, to which their standard overhead and profit are applied, as they still incur administrative costs and expect a return on managing that portion of the work.

Why the other options are wrong

  • B. Allowances are part of the contract scope, not separate optional costs.
  • C. Adding a contingency to the allowance is not the standard way to incorporate an allowance; the allowance itself is the agreed-upon amount.
  • D. Overhead and profit should typically be applied to allowances, as the contractor still manages this portion of the work.

Contract Allowance

A specified sum of money included in the contract documents for a particular item or scope of work that is not yet fully defined or selected.

  • Used when exact costs are unknown at bid time.
  • Contractor usually applies overhead and profit to the allowance.
  • Client pays difference if actual cost exceeds allowance, or receives credit if less.

Memory trick: Allowances are like a gift card: it's part of the total, and you still charge for handling it.