CSLB C-33 Painting & DecoratingPlanning and EstimatingHard

A painting contractor is bidding on a new commercial construction project. The project specifications include a 'cash allowance' for the final color selection, to be chosen by the owner at a later date. The allowance is $5,000 for materials. The contractor's overhead rate is 15% and profit margin is 10% on costs. How should the contractor calculate the total amount to include in the bid for this allowance?

  1. A$5,000.00
  2. B$6,325.00
  3. C$5,750.00
  4. D$5,500.00
Show answer & explanation

Correct answer: B. $6,325.00

The allowance ($5,000) is treated as a direct cost. First, add overhead: $5,000 * 1.15 = $5,750. Then, add profit to this new subtotal: $5,750 * 1.10 = $6,325.00. This ensures the contractor recovers administrative costs and earns profit on managing the allowance.

Why the other options are wrong

  • A. This only includes the direct material cost, ignoring overhead and profit.
  • C. This includes overhead but neglects to apply profit (5,000 * 1.15 = 5,750).
  • D. This only adds profit to the initial allowance, ignoring overhead (5,000 * 1.10 = 5,500).

Allowance with O&P Calculation

The process of adding a contractor's standard overhead and profit percentages to a specified allowance amount to determine its total inclusion in the bid.

  • Allowance is treated as a direct cost.
  • Overhead is added first to the allowance.
  • Profit is then added to the subtotal (allowance + overhead).

Memory trick: Allowance is a 'cost', then add O&P in layers.

More Planning and Estimating questions