Project Management Professional (PMP)® Examination Content OutlineProcessMedium

A project manager is leading a project to upgrade an organization's IT infrastructure. During the planning phase, the team identifies a potential risk: a critical vendor might fail to deliver specialized hardware on time, which could delay the entire project by several weeks. The project manager wants to implement a proactive strategy to reduce the probability or impact of this risk. Which of the following is an example of a 'risk mitigation' strategy?

  1. ADeveloping a contingency plan to use an alternative, readily available hardware if the primary vendor fails.
  2. BAccepting the risk and documenting it in the risk register without further action.
  3. CTransferring the risk to an insurance company by purchasing a project delay policy.
  4. DInsisting on a penalty clause in the contract with the critical vendor for late delivery.
Show answer & explanation

Correct answer: A. Developing a contingency plan to use an alternative, readily available hardware if the primary vendor fails.

Risk mitigation aims to reduce the probability or impact of a negative risk event. Developing a contingency plan to use alternative hardware directly reduces the impact of the vendor's late delivery, making it a mitigation strategy. A penalty clause is a form of transference, accepting the risk is not proactive, and insurance is also transference.

Why the other options are wrong

  • B. Accepting the risk is a valid response, but it's not a proactive mitigation strategy; it's a decision to take no further action.
  • C. Purchasing insurance is a classic example of risk transference, moving the financial burden to a third party.
  • D. A penalty clause is a form of risk transference, as it aims to shift the financial consequence of the risk, not reduce its probability or impact.

Risk Mitigation

A risk response strategy that aims to reduce the probability of a negative risk event occurring and/or reduce its impact if it does occur.

  • Involves taking proactive steps to lessen risk exposure.
  • Focuses on reducing either likelihood or consequence.
  • Examples include testing, prototyping, redundant systems, or alternative plans.

Memory trick: Dodge the bullet, build a shield, or pass the burden to another field.