Project Management Professional (PMP)® Examination Content OutlineProcessMedium

A project manager is leading a project to develop a new cloud-based data analytics platform. The project is nearing completion, and the team has successfully delivered all planned features. However, the initial business case for the project highlighted a target of a 15% reduction in operational reporting time, which has not yet been formally verified by the business unit. What should the project manager do NEXT?

  1. ADocument the unverified benefit as a lesson learned for future projects.
  2. BExtend the project duration to allow the business unit more time to verify the benefit.
  3. CProceed with the final project closure activities, as all features are delivered.
  4. DConduct a benefits realization review with the business unit to verify the achievement of the 15% reduction target.
Show answer & explanation

Correct answer: D. Conduct a benefits realization review with the business unit to verify the achievement of the 15% reduction target.

Project success is not solely about delivering features; it's also about realizing the intended benefits. Before final closure, especially if a specific benefit was targeted, the project manager should facilitate a benefits realization review to confirm if the project has achieved its strategic objectives and delivered the expected value.

Why the other options are wrong

  • A. Documenting as a lesson learned is a good practice, but it doesn't address the immediate need to verify the benefit for the current project.
  • B. Extending the project duration solely for benefit verification might not be necessary; a dedicated review is more appropriate than delaying project closure.
  • C. Closing the project without verifying benefits means the project's true success and value delivered remain unconfirmed.

Benefits Realization Review

A formal assessment conducted to determine if the expected benefits outlined in the business case or benefits management plan have been achieved by the project's deliverables.

  • Often conducted post-project or at key milestones.
  • Measures the actual value delivered.
  • Involves business stakeholders and project team.

Memory trick: Before you close, 'SEE' if the benefits are true.

More Process questions