Project Management Professional (PMP)® Examination Content OutlineProcessEasy

A project manager is leading a project with a budget of US$1,200,000. At the 50% completion mark, the Earned Value (EV) is US$500,000, and the Actual Cost (AC) is US$600,000. What is the Cost Performance Index (CPI) for this project?

  1. A1.11
  2. B0.90
  3. C0.83
  4. D1.20
Show answer & explanation

Correct answer: C. 0.83

The Cost Performance Index (CPI) is calculated as Earned Value (EV) divided by Actual Cost (AC). In this case, CPI = US$500,000 / US$600,000 = 0.8333, which rounds to 0.83.

Why the other options are wrong

  • A. This is likely a miscalculation or incorrect formula application.
  • B. This is likely a miscalculation or incorrect formula application.
  • D. This would be AC/EV, which is incorrect for CPI.

Cost Performance Index (CPI)

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

  • Formula: CPI = EV / AC.
  • CPI < 1 indicates a cost overrun (over budget).
  • CPI > 1 indicates a cost underrun (under budget).

Memory trick: Earned over Actual, tells if you're a saver or a squanderer.

More Process questions