Project Management Professional (PMP)® Examination Content OutlineProcessHard

A project manager is managing a project with a budget of US$500,000 and a planned duration of 10 months. At the end of month 5, the project has spent US$280,000. The Earned Value (EV) calculation shows that the value of work completed is US$250,000. What is the Cost Performance Index (CPI) for this project, and what does it indicate?

  1. ACPI = 1.12, indicating the project is over budget.
  2. BCPI = 0.89, indicating the project is under budget.
  3. CCPI = 0.89, indicating the project is over budget.
  4. DCPI = 1.12, indicating the project is under budget.
Show answer & explanation

Correct answer: C. CPI = 0.89, indicating the project is over budget.

The Cost Performance Index (CPI) is calculated as Earned Value (EV) divided by Actual Cost (AC). In this case, EV = US$250,000 and AC = US$280,000. So, CPI = 250,000 / 280,000 = 0.89. A CPI less than 1.0 indicates that the project is over budget, meaning it is getting less value for the money spent.

Why the other options are wrong

  • A. The calculation is incorrect, and the interpretation of CPI > 1.0 is incorrect for 'over budget'.
  • B. The calculation is correct, but the interpretation of CPI < 1.0 as 'under budget' is incorrect.
  • D. The calculation is incorrect, and the interpretation of CPI > 1.0 is incorrect for 'under budget'.

Cost Performance Index (CPI)

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

  • Formula: CPI = EV / AC (Earned Value / Actual Cost).
  • CPI > 1.0 indicates under budget (good).
  • CPI < 1.0 indicates over budget (bad).
  • CPI = 1.0 indicates exactly on budget.

Memory trick: EVM tracks project value for money, spotting budget and schedule health.

More Process questions