CompTIA Project+ (PK0-005)Project Life Cycle PhasesMedium

During project initiation, a project manager compiles a list of all individuals and groups affected by the project, along with their influence, interest, and communication needs. Which document is being created?

  1. AProject schedule
  2. BIssue log
  3. CResponsibility assignment matrix
  4. DStakeholder register
Show answer & explanation

Correct answer: D. Stakeholder register

The stakeholder register is created during initiation to identify all stakeholders and document their interest, influence, and engagement needs, forming the basis for later stakeholder management planning. A RACI matrix, issue log, and schedule are developed for different purposes later in the life cycle.

Why the other options are wrong

  • A. A timeline of activities built during planning, unrelated to stakeholder data.
  • B. Tracks open issues during execution/monitoring, not initiation.
  • C. Assigns roles and responsibilities for tasks, developed during planning.

Stakeholder Register

An initiation-phase document listing all identified project stakeholders along with their interest, influence, and engagement requirements.

  • Created early, alongside the charter and business case
  • Feeds into the stakeholder engagement/communication plan
  • Should be updated throughout the project as stakeholders change

Memory trick: 'Business, Charter, Stakeholders, Scope' - build the foundation before planning starts.