CompTIA Project+ (PK0-005)Project Life Cycle PhasesMedium

Before committing budget and resources, an organization wants to determine whether a proposed data center migration is technically achievable and financially justified. Which initiation activity should be performed?

  1. AFeasibility study
  2. BKickoff meeting
  3. CRisk register development
  4. DWBS creation
Show answer & explanation

Correct answer: A. Feasibility study

A feasibility study assesses whether a proposed project is technically achievable, financially viable, and practical before formal commitment of resources. Kickoff meetings and WBS creation occur later in planning/execution, and risk registers are developed during planning.

Why the other options are wrong

  • B. Kickoff meetings occur after the project is approved and planned.
  • C. Risk registers are built during planning, not before project approval.
  • D. WBS creation happens during planning, after feasibility is confirmed.

Feasibility Study

An analysis performed during initiation to determine whether a proposed project is technically, financially, and operationally viable.

  • Performed before formal project approval
  • Assesses technical, financial, and operational viability
  • Helps decide go/no-go on a proposal

Memory trick: Feasibility = 'Is it feasible?' checked first