CompTIA Project+ (PK0-005)Project Life Cycle PhasesMedium

A project manager is leading a large, complex IT infrastructure upgrade. Multiple teams are involved, and their activities have numerous interdependencies. To effectively visualize the sequence of work and identify potential bottlenecks, the project manager creates a graphical representation showing the logical relationships between project activities. What is this representation called?

  1. ANetwork Diagram
  2. BGantt Chart
  3. CWork Breakdown Structure (WBS)
  4. DResource Histogram
Show answer & explanation

Correct answer: A. Network Diagram

A network diagram is a visual representation of the sequence of activities and their logical relationships in a project schedule.

Why the other options are wrong

  • B. A Gantt Chart is a bar chart showing the start and finish dates of project activities, but it doesn't explicitly show logical relationships as clearly as a network diagram.
  • C. A Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work, not a representation of activity sequences.
  • D. A Resource Histogram is a bar chart showing the number of resources required over time, not the sequence of activities.

Network Diagram

A graphical representation of the logical relationships among the project schedule activities.

  • Shows activity sequence and dependencies.
  • Used to calculate the critical path.
  • Helps identify potential bottlenecks and float.

Memory trick: Network diagrams map activity flows.