CompTIA Project+ (PK0-005)Project Life Cycle PhasesEasy

A client hires a vendor to develop a custom kitchen renovation. Before work begins, the client provides a document that specifies the exact work to be performed, deliverables, timeline, and acceptance criteria the vendor must meet. Which document is this?

  1. AStatement of Work
  2. BBusiness Case
  3. CWBS Dictionary
  4. DProject Charter
Show answer & explanation

Correct answer: A. Statement of Work

A Statement of Work (SOW) defines the specific work, deliverables, timeline, and acceptance criteria for a vendor or contractor engagement. The charter authorizes the project internally, the WBS dictionary defines work packages, and the business case justifies the investment.

Why the other options are wrong

  • B. A business case justifies whether to invest, not the vendor's scope of work.
  • C. The WBS dictionary describes internal work packages, not vendor contracts.
  • D. The charter authorizes the project and names the PM, not vendor deliverables.

Statement of Work (SOW)

A document describing the work, deliverables, timeline, and acceptance criteria for a vendor or contractor.

  • Used primarily in procurement/contracting
  • Defines scope of vendor deliverables
  • Includes acceptance criteria and timeline

Memory trick: SOW = Scope Of Work you sow with a vendor