CompTIA Project+ (PK0-005)Project Life Cycle PhasesEasy

During the execution phase of a software development project, a critical team member unexpectedly resigns. This departure creates a significant risk to the project schedule and budget. Which of the following project documents should the project manager consult FIRST to understand the procedures for addressing such an event?

  1. ARisk Management Plan
  2. BStakeholder Register
  3. CWork Breakdown Structure (WBS)
  4. DProject Charter
Show answer & explanation

Correct answer: A. Risk Management Plan

The Risk Management Plan outlines how risks will be identified, analyzed, and responded to. The unexpected resignation of a critical team member is a project risk, and this plan would contain the procedures for handling such an event, including mitigation strategies or contingency plans.

Why the other options are wrong

  • B. The Stakeholder Register lists project stakeholders and their interests, not procedures for managing project risks.
  • C. The WBS decomposes project deliverables into smaller work packages, not risk management procedures.
  • D. The Project Charter authorizes the project and provides high-level objectives, but not detailed risk response procedures.

Risk Management Plan

A component of the project management plan that describes how risk management activities will be structured and performed for the project.

  • Defines how risks are identified, analyzed, and responded to.
  • Includes roles and responsibilities for risk management.
  • Outlines risk categories and probability/impact scales.

Memory trick: When risks arise, the plan guides your enterprise.