CompTIA Project+ (PK0-005)Project Life Cycle PhasesHard

A project manager is developing the project schedule and needs to estimate the duration of a new, highly uncertain research activity. Due to the high uncertainty, a single point estimate is unreliable. The project manager decides to use three estimates: an optimistic (O), a pessimistic (P), and a most likely (M) estimate. Which estimation technique is being applied?

  1. AThree-Point Estimating (PERT)
  2. BBottom-Up Estimating
  3. CAnalogous Estimating
  4. DParametric Estimating
Show answer & explanation

Correct answer: A. Three-Point Estimating (PERT)

Three-Point Estimating, often associated with PERT, uses optimistic, pessimistic, and most likely estimates to calculate a weighted average duration, providing a more reliable estimate for uncertain activities.

Why the other options are wrong

  • B. Bottom-Up Estimating involves estimating the cost or duration of individual work packages or activities with the greatest level of detail.
  • C. Analogous Estimating uses data from previous, similar projects to estimate cost or duration.
  • D. Parametric Estimating uses a statistical relationship between historical data and other variables to calculate an estimate.

Three-Point Estimating (PERT)

An estimation technique that uses optimistic (O), pessimistic (P), and most likely (M) estimates to calculate a weighted average duration or cost.

  • PERT formula: (O + 4M + P) / 6.
  • Provides a range of possible outcomes.
  • Useful for activities with high uncertainty.

Memory trick: Analogous is past, Parametric is math, Bottom-Up is small, Three-Point is uncertain.

More Project Life Cycle Phases questions