CSLB General Building (B)Mechanical, Electrical, Plumbing CoordinationEasy

An electrician bores a hole through the center of a 2x4 stud for NM cable, and the hole edge ends up located 3/4 inch from the face edge of the stud. According to NEC requirements as applied in residential wiring, what must be installed to protect the cable?

  1. AA double stud must be installed at that location
  2. BThe cable must be rerouted through the top plate instead
  3. CNo protection is required since the hole is within the stud
  4. DA 1/16-inch thick steel plate covering the area of the cable
Show answer & explanation

Correct answer: D. A 1/16-inch thick steel plate covering the area of the cable

NEC 300.4(A)(1) requires a steel plate or bushing at least 1/16 inch thick when a bored hole is located less than 1-1/4 inches from the nearest edge of the framing member, to protect the cable from screws or nails.

Why the other options are wrong

  • A. Doubling the stud is not a code remedy for insufficient cable clearance.
  • B. Rerouting through the top plate does not address the exposed cable hazard at this stud location.
  • C. Protection is required because the hole is closer than 1-1/4 inches to the stud edge.

Bored Hole Cable Protection

NEC 300.4(A)(1) requires steel protective plates when wiring passes through framing holes closer than 1-1/4 inches to the framing edge, to prevent nail/screw punctures.

  • Minimum 1-1/4 inch clearance avoids need for a plate.
  • Steel plates must be at least 1/16 inch thick.
  • Applies to both bored holes and notches in framing.

Memory trick: 'Too close to the edge? Steel plate saves the wedge (cable).'

More Mechanical, Electrical, Plumbing Coordination questions