CSLB C-39 Roofing ContractorLow-Slope RoofingMedium

An elastomeric roof coating is applied at 24 dry mils and loses approximately 3 mils per year due to UV exposure and weathering. The manufacturer recommends recoating once thickness drops to 12 dry mils. In how many years should the recoat be scheduled?

  1. A8 years
  2. B4 years
  3. C6 years
  4. D3 years
Show answer & explanation

Correct answer: B. 4 years

The coating can lose (24 − 12) = 12 mils before reaching the minimum. At 3 mils/year loss rate, 12 ÷ 3 = 4 years until recoating is needed.

Why the other options are wrong

  • A. This overestimates the coating's service life beyond the calculated threshold.
  • C. This would require an unrealistically low loss rate.
  • D. This underestimates the allowable mil loss before recoating.

Coating Recoat Interval Calculation

A method for scheduling recoat maintenance by dividing the allowable mil loss (initial minus minimum thickness) by the annual wear rate.

  • Formula: (Initial mils - Minimum mils) ÷ Annual loss rate
  • UV exposure and weathering cause gradual mil loss
  • Manufacturers specify minimum functional mil thickness

Memory trick: Subtract, then divide, to find when to re-hide.